The two companies signed a deal which will allow the world's largest contract chip manufacturer to purchase all power produced by Ørsted's 920-megawatt wind farms off the coast of Changhua County, according to a news release by the Danish firm.
The farms were expected to start operating and producing energy in 2025-2026, with the TSMC contract helping to move the project 'closer to a final investment decision,' Ørsted Offshore CEO
Before the Greater Changhua 2b and 4 wind farms planned to supply TSMC, the Danish company had already started building the Greater Changhua 1 and 2a offshore farms.
The two companies praised each other for taking a major step in