STORY: :: Crews in Baltimore set off a controlled explosion to

help free a portion of the collapsed Francis Scott Key Bridge

:: May 13, 2024

The detonations broke the bridge's truss into small sections, enabling salvage crews to use cranes and barges to haul away the twisted metal wreckage, the U.S. Army Corps of Engineers said. The work had been planned for Sunday but it was delayed because of weather conditions.

In the early morning of March 26, the Dali lost power and crashed into a bridge support, sending the span into the Patapsco River, with a major portion draped over the Dali's bow. Six construction workers were killed.

The incident initially halted traffic at the Port of Baltimore, which ranks first in the United States in several cargo categories, including autos and light trucks, farm and construction machinery, imported sugar and imported gypsum, according to the state of Maryland.

Since the crash, four temporary channels have been opened, allowing for some shipping to resume. The Corps said it aims to restore port access to full capacity by the end of May.

Maryland estimates it will cost $1.7 billion to $1.9 billion to rebuild the bridge and anticipates completion by fall 2028.