Far West Gold Recoveries, phase 1: early-stage commissioning in progress
DRDGOLD LIMITED
(Incorporated in the Republic of South Africa)
(Registration number 1895/000926/06)
JSE share code: DRD
ISIN: ZAE000058723
NYSE trading symbol: DRD
('DRDGOLD' or the 'Company')
FAR WEST GOLD RECOVERIES, PHASE 1: EARLY-STAGE COMMISSIONING IN
PROGRESS
DRDGOLD is pleased to advise shareholders that the commissioning of the Far West Gold
Recoveries project, previously the West Rand Tailings Retreatment Project is set to start on
6 December 2018 with the pumping of reclaimed tailings into the carbon-in-leach circuit, just
four months into the construction of Phase 1. Far West Gold Recoveries was acquired from
Sibanye Gold Limited, trading as Sibanye-Stillwater, at the end of July 2018.
DRDGOLD´s CEO, Niël Pretorius, commented: 'The project is on track to achieve full
production of 500 000tpm from Phase 1 in the first quarter of 2019.'
As part of early-stage commissioning, face has been established at the Driefontein 5 tailings
dam reclamation site, from which pumping of reclaimed tailings through a new 2km pipeline
to the Driefontein 2 plant is set to begin. A parallel pipeline to return water from the plant to
the reclamation site has been completed.
Work to upgrade the plant´s retreatment capacity is well advanced, with carbon loading -
also part of the overall commissioning process - set to begin immediately.
An 8km pipeline to transport retreated tailings from the plant for cyclone deposition on the
Driefontein 4 tailings dam and a parallel return water pipeline from the deposition site to the
plant have also been completed.
Johannesburg
3 December 2018
Sponsor
One Capital
Date: 03/12/2018 11:22:00 Produced by the JSE SENS Department. The SENS service is an information dissemination service administered by the JSE Limited ('JSE').
The JSE does not, whether expressly, tacitly or implicitly, represent, warrant or in any way guarantee the truth, accuracy or completeness of
the information published on SENS. The JSE, their officers, employees and agents accept no liability for (or in respect of) any direct,
indirect, incidental or consequential loss or damage of any kind or nature, howsoever arising, from the use of SENS or the use of, or reliance on,
information disseminated through SENS.
Attachments
Original document
Permalink
Disclaimer
DRDGOLD Limited published this content on 03 December 2018 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 03 December 2018 09:36:12 UTC
DRDGOLD Limited is a South Africa-based holding company. The Company is primarily involved in the retreatment of surface gold tailings. The Companyâs business includes Ergo, Far West Gold Recoveries (FWGR), Hot Button Features and Resources and Reserves. Ergo business is a surface gold retreatment operation, which treats old slime dams and sand dumps to the south of Johannesburgâs central business district, as well as the East and Central Rand goldfields. The operation comprises three plants. The Ergo and Knights plants operate as metallurgical plants. The Ergo plant treats around 1.7 Mtpm of material. The City Deep plant operates as a pump/milling station feeding the metallurgical plants. The Companyâs FWGR is a surface gold retreatment operation that treats old slime dams in the West Rand goldfields and is located near Carletonville in South Africaâs Gauteng province. Mineral Resources consist of sand dumps, slimes dams and silted areas and dams.