Each transformer was transported in a separate lot. Within the frames of the project, FESCO specialists developed an individual transportation scheme and ensured the delivery of transformers fr om Novorossiysk to the installation sites at CHPPs.

Transshipment and loading in port were carried out directly from ships to special railway transporters, on which oversized cargo was transported to stations of the Moscow railway, wh ere transformers were loaded onto motor vehicles. On the sites of central heating and power plants the unloading of transformers was carried out by a rigging method with further movement to transformer tracks and installation on special transformer carriages. The equipment was delivered safely and in the exact agreed time.

The total time of the project was three months, taking into account the breaks between delivery of separate lots, the average time of transportation of each lot was 15-20 days.

Attachments

  • Original document
  • Permalink

Disclaimer

FESCO - Far Eastern Shipping Company OJSC published this content on 23 May 2018 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 23 May 2018 08:17:02 UTC