The Working Unit Kicevo - Ohrid is established by the decision of the Management Board of Granit in May 2014, in order to construct the Motorway Kicevo - Ohrid, section Kicevo - Podvis.

According to the Contract for construction of the Motorway:
- Granit Construction Stock Co. is nominated subcontractor;
- Sinohydro Corporation Limited is Main Contractor
- Consorcium GIM, Euroconsulting and Geing Krebs und Kiefer is Engineer;
- Public Enterprise for state roads is Employer.

The total price of the Contract for construction of the Motorway Kicevo - Ohrid, section Kicevo - Podvis is 117.609.360,15 euro.
Reinforced concrete works of the Motorway participate with more than 60% in the total price of the Contract for construction of the Motorway.

The time period for completion is 38 months from the commencement date.

Section Kicevo - Podvis consists of the following structures:
12 viaducts with prestressed beam girders, with total length of 3,60 km in both directions;
2 viaducts with balanced cantilevered method of construction, with total length of 1,80 km
2 overpasses
1 underpass with an interchange on the Motorway
Retaining walls with total length of 1,35 km

The critical points on the critical path of the Motorway Kicevo - Ohrid, section Kicevo - Podvis are the viaducts with balanced cantilevered method of construction, located at km 6+860 and km 9+105