Maxim Power Corp. announced it has successfully commissioned its 204 MW natural gas-fired power plant (“M2”) located near Grande Cache, Alberta. M2 began generating electricity to the Alberta power grid on May 8, 2020 during commissioning and successfully demonstrated its maximum generating capacity and environmental compliance during this final phase of construction. The company completed construction and commissioning of M2 despite challenging construction conditions related to both weather and COVID-19. This project represents an industry leading 16 month construction duration and 21 month total project horizon (from equipment procurement to project completion). M2 is the largest simple cycle natural gas-fired power plant in Alberta and is a significant milestone in the province’s transition away from coal-fired generation. The M2 project is a testament to the Government of Alberta’s ongoing commitment to promote economic development by creating a stable and attractive investment climate. The project created more than 120 jobs during the course of its construction and now provides ongoing employment and support of local businesses in the Grande Cache area of Alberta. The government's work to ensure federal carbon policy does not inhibit investment and its introduction of the made-in-Alberta TIER program are important to this project and to the company’s significant commitment to investing in Alberta’s power infrastructure.