6 months before the beginning of next repair and operational period 'IDGC of the South' JSC ('Rosseti' group) by the results of preliminary discussion of repair programmes of branches has determined the necessary amount and types of repair works, and expenses to provide reliable power supply of the customers and to get ready toautumn and winter period of 2016-2017.

In 2016 IDGC of the South plans to repair 13.6 thousand km of high-voltage power transmission lines of different voltage, to clear 1047 hectares of routes of overhead lines, to improve the operation of more than three thousand 6-10/0.4kV transformer substations and 47 substations of 35-110kV. The Company plans to spend 1 265 million rubles on these works, it is 15% more than the planned limits. Percentage of in-house method of repair programme implementation amounts 86%, and contracting method - 14%.

This year the Company has been using modern information technologies for planning - system of productive assets management (SUPA). It allows to set precise volume of repair works in accordance with risks of providing of reliable electric supply, comply with operating requirement of productive assets and reduce percentage of unscheduled repair works.

distributed by