A labyrinth of endlessly winding pipes, tall smokestacks and intertwined structures is what the workers in blue helmets and blue protective uniforms confidently wind their way through.
They busy themselves with turning valves, welding pipes and putting up the scaffolding. They get on their bicycles to reach their work locations more quickly - the 320 hectares of the TOTAL refinery Mitteldeutschland are equal to 500 soccer fields put together. A 140-meter-high flare stack, its flame burning night and day, towers over the plant and is visible from afar. The refinery could aptly be described as a self-contained world of its own.
TOTAL's refinery Mitteldeutschland in Leuna is one of the most modern industrial plants in
The technicians deployed here by the Mannheim-based industrial services provider Bilfinger are no strangers to the challenges that the plant and its operation present in practice. For 24 years now, the company has been working with the refinery in Leuna, assisting with various modernization and expansion measures, for example. Only recently, the
The first of them - replacing the six reactor systems - will have to be carried out in the midst of ongoing production operations and, if at all possible, without any downtimes. This is because the reactor systems, along with the downstream plant components, convert heavy petroleum residues from the refinery into methanol, a key industrial input chemical, by means of partial oxidation (POX). This will be the most extensive refurbishment work ever done on the Leuna plant, which is one of the last industrial holdovers from the Communist period in
A project of this magnitude requires careful advance preparation; accordingly, planning was begun as early as at the start of 2019.
The project's logistics present a particular challenge: The plant components to be installed are big and heavy. Thus, a special crawler crane with a capacity of 600 tons will be used to fit the reactors into place. Several days will be needed just to set up and remove the crane and to prepare its operating lane - a process that will have to be repeated for each of the six reactors. Transporting the crane and its appurtenant equipment will require some 50 trucks. Weber provides the details: 'So you see that our services consist of more than the pre-assembly work and the conversion as such. Just as important is our preparatory planning and our coordination of the various trades on the construction site. In the end, everything has to run like clockwork. It's high-precision work. Of course, safety always comes first.' The reactors are scheduled to be replaced by the end of 2021, thereby completing the project.
By this time, the second contract awarded to Bilfinger - the refinery's turnaround in the fall of 2020 - will also have been completed.
In order to keep such downtimes as short as possible, Bilfinger has developed its own in-house concept for executing turnarounds. 'How we go about it exactly is a trade secret,' says Braune and laughs: 'But I can say this much: Efficient scheduling and work planning are essential. Another factor is that our workforce is highly qualified and very familiar with the routines involved in such interventions. What's more, we're using digital solutions to an increasing degree.' The results speak for themselves: Every year, Bilfinger performs around 30 comprehensive turnarounds of industrial plants across
This hopefully will hold true also for the turnaround of the TOTAL refinery Mitteldeutschland. Bilfinger acts as general contractor for a number of the plant's systems, including the POX methanol facility. The maintenance services, which have been planned far in advance, must be completed within four to six weeks. This will involve opening, inspecting and cleaning innumerable containers and pipes - and of course also repairing them if needed. Subsequently, the individual components will be inspected and certified by the
To ensure that this is the case, giant workflow diagrams wallpaper have been hung up where everyone can see them. These depict the individual work steps and work packages, which can then be checked off as they are completed. Thus, everyone will be able to keep an eye on the big picture. As Braune puts it, 'A turnaround is a like a vast mosaic composed of many small tiles representing work packages, one that has been painstakingly planned two years in advance.' In fact, a planning period this long is indispensable: Certain portions of the plant will be turned into huge construction sites for short periods of time, where many people will be expected to work in coordination at very close quarters. It goes without saying that, despite the intense time pressure involved, occupational safety and diligence will always have top priority.
With these two projects, Bilfinger will support the