Genoa, 21 June 2019 - ERG is pleased to announce that the construction and commissioning phase for the Linda wind farm, located in the German region of Saxony - Anhalt, has been completed.

The wind farm, which in the auction held on 1 May 2018 was assigned a tariff of approximately 65 Euro/MW/h, including the correction factor, for a period of 20 years, has a capacity of 21.6 MW and estimated annual output when fully operational of 50 GWh, corresponding to around 39,000t per year of avoided CO2 emission.

With the coming into operation of Linda, ahead of schedule compared to the date envisaged in the Business Plan, ERG reaches 238 MW of installed wind power capacity in Germany and continues to pursue its organic growth path in one of the target European countries, in keeping with the Plan objectives.

For further information, please refer to our Press Releases dated 15/1/2018 and 18/5/2018.

Contacts:

Sabina Alzona Media Relations Manager - tel. + 39 010 2401804 cell. + 39 340 1091311 - e-mail: salzona@erg.eu

Emanuela Delucchi IR Manager - tel. + 39 010 2401806 - e-mail: ir@erg.eu

Matteo Bagnara IR - tel. + 39 010 2401423 - e-mail: ir@erg.eu

www.erg.eu - @ergnow