LUKOIL INSTALLS ACCOMMODATION PLATFORM JACKET AT V.I. GRAYFER FIELD

Monday, May 25, 2020

LUKOIL completed installation of a jacket for an accommodation platform topside at the V.I. Grayfer field in the Caspian Sea. The offshore operations involved 110 workers and nine vessels.

The facility was brought to the offshore installation site via the Volga-Caspian Shipping Canal. After the floatover and grounding, the substructures were fixed with ten piles of 56 meters in length each and with a total weight of 1 700 tonnes. When installed and fixed, the facility was inspected by divers.

Like all other platforms of the company in the Caspian Sea, quarters platform jacket was constructed at shipyards of the Astrakhan Region. The design life of the facility is 35 years. Built to endure significant ice loads, the jacket was engineered with special consideration of safety and environmental protection requirements.

The company plans to install a jacket for its offshore ice-resistant fixed platform at the same field, later this year, and mount topsides of the accommodation and the ice-resistant platforms on the substructures in 2021. Production at the V.I. Grayfer field is scheduled for 2022. The field's annual planned production rate is 1.2 million tonnens of oil.

  • Press release in PDF
Contact information

Press Centre PJSC 'LUKOIL'

media@lukoil.com

+7 (495) 627-16-77

http://www.lukoil.com

https://www.facebook.com/Lukoil.en

http://twitter.com/lukoilengl

You may be interested
27/04/2020 -LUKOIL SIGNED MEMORANDUM ON PRODUCTION OF SULZER OILFIELD SERVICE EQUIPMENT IN KOGALYM

LUKOIL has signed a trilateral memorandum with Sulzer Ltd. and Kogalym Oilfield Equipment Service LLC (KNPO). The memorandum envisages the localization of spare parts production for energy-efficient pumping equipment in Kogalym.

26/06/2019 -LUKOIL MAKING GOOD HEADWAY WITH PRIORITY PROJECTS IN THE CASPIAN SEA

LUKOIL is successfully evolving its priority projects in the north of the Caspian Sea. The company continues to construct facilities at Vladimir Filanovsky, Yury Korchagin and Rakushechnoye fields.

16/10/2018 -LUKOIL STARTS THE CONSTRUCTION OF FACILITIES AT RAKUSHECHNOYE FIELD

​President of LUKOIL Vagit Alekperov, jointly with Head of the Astrakhan Region Sergey Morozov, took part in the official groundbreaking ceremony to mark the start of construction of infrastructure facilities of Rakushechnoye field. ​

Commercial oil production, with an estimated plateau level of 1.2 million tonnes, is expected to commence in 2023. ​