Merlin Diamonds Limited
ABN 86 009 153 119
23 July 2018
Manager Companies Australian Securities Exchange Level 6, 20 Bridge Street Sydney NSW 2000
By E-Lodgement
Merlin to Double Ore Processing Capacity with New Scrubber
Merlin Diamonds Limited ABN 86 009 153 119
Level 1A
42 Moray Street Southbank, VIC, 3006
Australian diamond mining company Merlin Diamonds Limited (ASX: MED) ("Merlin" or "the Company") reports that with the scaling up of mining activities at the Merlin Diamond Mine in the Northern Territory, ore processing capacity will double with the installation of a new scrubber.
Telephone: +61 3 8532 2858
www.merlindiamonds.com.au
Processing will increase from the 50 tonnes per hour to 100 tonnes per hour, thus doubling the production of diamonds. The new scrubber, screen and conveyor belts are being prepared for shipping and are expected to arrive at Merlin in late August. Merlin's team conducted a final inspection last week prior to shipping (see figures 1-4 below).
Directors
Mr Joseph Gutnick Executive Chairman
The scrubber will also significantly reduce the recirculation of oversize material and give Merlin the ability to feed damp ore directly from the pit.
Mr Mordechai Gutnick Managing Director
As well, Merlin has purchased a jaw crusher which will be introduced into the processing circuit to treat the trommel oversize material (see figure 5).
Mr Henry Herzog Non-Executive Director
As previously advised, a Dense Medium Separation (DMS) circuit has also been ordered from South Africa, and once installed, capacity will increase upwards of 150 tonnes per hour.
Dr David S Tyrwhitt Non-Executive Director
Further updates on mining operations will be provided shortly as mining contractor Rusca Bros Services ramps up activities at site.
Senior Management
Mr Peter Lee
-ENDS-
CFO & Company Secretary
Mr Joshua Harper General Manager Operations
JOSEPH GUTNICK Executive Chairman
Merlin Diamonds Limited July 2018 Progress Update
Merlin Diamonds Limited
ABN 86 009 153 119
Figure 1: Trommel scrubber washing plant
Figure 2: High frequency vibrating screen
Merlin Diamonds Limited July 2018 Progress Update
Merlin Diamonds Limited
ABN 86 009 153 119
Figure 3: Conveyor belt
Figure 3: Schematic of second ore processing plant being installed
Merlin Diamonds Limited July 2018 Progress Update
Merlin Diamonds Limited
ABN 86 009 153 119
Figure 4: Jaw crusher to be installed shortly at Merlin Diamond Mine
Merlin Diamonds Limited July 2018 Progress Update
Attachments
- Original document
- Permalink
Disclaimer
Merlin Diamonds Limited published this content on 23 July 2018 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 23 July 2018 04:07:04 UTC