Highlights | |||
• | Progressing to plan with accelerated development: | ||
• | Main Shaft equipping advancing to plan | ||
• | Materials handling system complete and in position pending finalization of related civil works | ||
• | Plan for imminent restart of production confirmed: | ||
• | Mill restart is expected for mid-August | ||
• | Initial production will come from both existing stockpile and development ore | ||
• | Commencement of ore hoisting from Main Shaft in Q4 | ||
• | Full production capacity is expected to be achieved in Q4 | ||
• | Operational de-risking measures implemented: | ||
• | Cost reduction program completed over Q1 and Q2 | ||
• | New underground contractor performing to plan | ||
• | Simplified critical path plan adopted to enable restart operations with stope ore hoisting directly from Main Shaft, expediting ramp-up of ore volumes to mill | ||
• | Ore stockpile continues to grow, with lateral development focused on key infrastructure and building high-grade stope inventory | ||
• | Mill optimization completed during suspension period | ||
• | COVID-19 operating and contingency plans implemented | ||
• | Optionality to lock-in forward copper prices and de-risk forward revenues | ||
• | Management team build-out and strengthening |
“The Pumpkin Hollow management team is making excellent progress. Operational readiness is now well on-track and we are continuing the re-mobilisation of our workforce. We are entering exciting times as we prepare to commission the Main Shaft and plan to bring the Pumpkin Hollow underground mine into full scale production in the fourth quarter.”
Accelerated Development Progress on Track
Progress on the previously announced accelerated development plan remains on track:
• | Main Shaft | ||
• | As announced on | ||
• | The main materials handling infrastructure is complete and positioned immediately adjacent to the shaft headframe. On completion of the civil works, the materials handling system will be relocated into its final location. This will allow for the completion of electrical fit out and alignment with the ore haulage conveyance. | ||
• | Lateral development: | ||
• | Lateral development rates are in line with target, and additional optimization measures are being implemented to further increase productivities to exceed budgeted rates. | ||
• | Hoist rates for the Vent Shaft are consistently 1000 tons/day, which is 300 tons/day above initial target. Material quantities of ore continue to be hoisted daily, as a large proportion of development ore is above cut-off grades. | ||
• | In addition to key infrastructure, lateral development is focused on high-grade ore development and the preparation of stoping panels for the commissioning of the Main Shaft. |
Planned Restart and Ramp-up Timeline
The phased re-mobilization of workforce is underway and expected to be completed this month, with the mill restart expected for mid-August.
Production during September and October is planned from stockpile and ongoing development ore hoisting. After this initial period, full hoisting is planned to commence from the Main Shaft, which will include high-grade stope ore.
Restart and Ramp-up Milestones
• | Main Shaft completion | ||
• | Main Shaft at final depth (completed June) | ||
• | Headframe and hoist changes (August) | ||
• | Shaft furnished with steel guides etc. (September) | ||
• | Loading pocket completion (October) | ||
• | Final shaft configuration and hoisting system commissioned (October/November) | ||
• | Ore & Stoping | ||
• | Development to prepare stope inventory to provide consistent feed for ramp-up (ongoing) | ||
• | Development ore hoisting to stockpile via Vent Shaft (ongoing) | ||
• | Ore grades further increasing as drifts enter bottom and tops of future stopes (August/September) | ||
• | Stoping commences in earnest with Main Shaft hoisting, benefiting from advanced stope development in place (November) | ||
• | Mill: | ||
• | Re-stocking of consumables and additional spares (in progress) | ||
• | Remaining personnel re-mobilized in stages ahead of mill restart (July) | ||
• | Mill restart (mid-August) | ||
• | Excess stockpile processed, maintaining a long-term floating stockpile to facilitate redundancy and blending capacity (August/September) |
The Company completed construction of its
During the suspension of milling, the Company limited its operating costs to preserve working capital where possible and continued to invest in its accelerated mine development plan.
With initial construction already completed, the restart of production will comprise the ramp back up of operating expenditures and ongoing sustaining capital, and revenues from production are expected to begin during Q3.
De-Risking Measures Implemented
• | |||
• | Replaced previous underperforming mine contractor with Redpath in Q1 2020. Redpath has progressed well at Pumpkin Hollow and has met operating targets | ||
• | Decoupled mine-to-mill during the current suspension period, allowing mine development to advance ahead delivering mine infrastructure and building stope inventory | ||
• | Focused on an accelerated critical path plan to simplify execution plan and allow for expedited route to full-scale hoisting capacity | ||
• | Building of larger ore stockpile on surface to de-risk mill start-up, and maintenance of long-term floating stockpile buffer | ||
• | Mill: | ||
• | Implemented learnings from Q1 ramp-up and undertook preventative maintenance during mill suspension | ||
• | Team build-out and strengthening: | ||
• | Hired new senior management personnel with a track record of successful mine ramp-up and driving operating efficiencies | ||
• | Cost reduction program: | ||
• | Cost reduction program undertaken during Q1 and completed in Q2. Implemented structural reductions in corporate overheads, site G&A, improved purchasing of goods and services | ||
• | Price protection: | ||
• | Arranged facility providing optionality to enter into rolling copper fixing hedges to lock-in forward copper prices and de-risk forward revenues |
The Company’s planned restart of production and ramp-up timeline as outlined above are subject to revision based on impacts of the COVID-19 pandemic and other factors.
Qualified Persons
The information and data in this news release was reviewed by
About
www.nevadacopper.com
For further information contact:
rmatthews@integcom.us
+1 604 355 7179
Cautionary Language
This news release includes certain statements and information that constitute forward-looking information within the meaning of applicable Canadian securities laws. All statements in this news release, other than statements of historical facts are forward-looking statements. Such forward-looking statements and forward-looking information specifically include, but are not limited to, statements that relate to the various impacts of the COVID-19 pandemic, mine development and ramp-up plans and the expected results and expenditures in respect thereof and the timing of expected restart of concentrate production, and plans in respect thereof.
Often, but not always, forward-looking statements and forward-looking information can be identified by the use of words such as “plans”, “expects”, “potential”, “is expected”, “anticipated”, “is targeted”, “budget”, “scheduled”, “estimates”, “forecasts”, “intends”, “anticipates”, or “believes” or the negatives thereof or variations of such words and phrases or statements that certain actions, events or results “may”, “could”, “would”, “might” or “will” be taken, occur or be achieved. Forward-looking statements or information are subject to known or unknown risks, uncertainties and other factors which may cause the actual results to be materially different from any future results, performance or achievements expressed or implied by such forward-looking statements or information.
Forward-looking statements or information are subject to a variety of risks and uncertainties which could cause actual events or results to differ from those reflected in the forward-looking statements or information, including, without limitation, risks and uncertainties relating to: the state of financial markets; regulatory approvals; the impact of COVID-19 on the business and operations of the Company; history of losses; requirements for additional capital; dilution; adverse events relating to construction, development and ramp-up, including the ability of the Company to address underground development and process plant issues; ground conditions; cost overruns relating to development, completion and ramp-up of the
The Company provides no assurance that forward-looking statements will prove to be accurate, as actual results and future events could differ materially from those anticipated in such statements. Accordingly, readers should not place undue reliance on forward-looking statements.
Source:
2020 GlobeNewswire, Inc., source