9 April, 2018

Pantheon Resources plc

Operational Update

Pantheon Resources plc ("Pantheon" or "the Company"), the AIM-quoted oil and gas exploration company with a 50% - 75% working interest in several conventional project areas in Tyler and Polk Counties, onshore East Texas, provides the following operational update.

VOBM#5 - Frac operations

Fracking operations commenced at VOBM#5 on 27 March 2018. The frac was executed on plan and on schedule with all frac fluid and proppant displaced as anticipated. After weather delays the well was placed into test on 30 March 2018. Gas production commenced in the following days along with frac fluid and later formation water.

The well was shut in for a short period to observe shut in pressure build up and then tested again. Following the recommencement of testing and after recovery of the majority of the frac fluid, the well tested at an average of 1150 mcfpd along with 170 bwpd and no oil, on a 10/64ths choke and 5900 psi flowing tubing pressure. During testing the well began freezing up and production flow was interrupted repeatedly. A decision was made to shut the well in until heaters become available, which is currently anticipated to be during the week commencing 9 April 2018. Testing will resume once these have been fitted.

Based upon the extremely good log responses for VOBM#5 which showed 60-feet of net pay in the targeted Eagle Ford sandstone, and which appeared superior to the logs of our VOBM#1 well and of comparable Double A Wells field wells, we expected to see very good flow rates. Therefore, the produced volumes of water and the fact that no oil has been produced is unexpected. It is believed that the frac most likely went down a fracture plane into a deeper water source which was not seen on the logs and the water produced is impeding hydrocarbon production. Additional analysis is being undertaken in conjunction with third party experts to better understand the behaviour of VOBM#5 and to determine the appropriate course of action for this well and our West AA acreage in Polk County.

By comparison, the nearby VOBM#1 well produced during its testing period at over 6000 mcfpd and over 500 bopd without formation water prior to its shut-in and the collapse of the casing in that well. The presence of such quantities of water in this well is anomalous when compared to all our other wells and to those wells which we believe to be analogous in the Double A Wells Field, none of which produced water at these rates, and all of which produced oil/condensate.

VOBM#1- Remediation works

The Company and operator have confirmed a remediation plan for the collapsed casing within the VOBM#1 well; to conduct a sidetrack operation or possibly a redrill. It is anticipated that remediation works will take c.45 days from their start, and it is our expectation that this should significantly increase production from this well. That operation will begin after analysis of VOBM#5 has been completed. The Company looks forward to reporting on the progress of this operation.

London Roadshow

Jay Cheatham, CEO, will be in London this week meeting with investors. The Company advises that it is not undertaking any fundraising activities.

Jay Cheatham, CEO, said:

"At the VOBM#5 discovery well, the representation of the Eagle Ford Sandstone in the log responses were some of the cleanest I have seen to date and, such logs would be expected to result in upper tier wells. It is perplexing that we have produced water in such quantity while on test and that production rates differ so much from the pre-shut in VOBM#1. We have one of the most experienced teams in the region addressing the issue and are using the time while we wait for heating elements to calibrate the seismic to the well logs to determine if we have encountered a deeper water bearing zone which was unseen on the logs and which is impeding hydrocarbon production. Once we have completed our analysis and have more production test data we will be in a far better position to assess the productivity of this well.

"I can also report that last week the operator and I met with one of the entities exploring the possibility of participating in a Wilcox and Navarro play on our Tyler County acreage.

Those discussions are ongoing."

-Ends -

Further information:

Pantheon Resources plc Jay Cheatham, CEO

+44 20 7484 5361

Justin Hondris, Director, Finance and Corporate Development

Stifel Nicolaus Europe Limited (Nominated Adviser and broker) Callum Stewart

+44 20 7710 7600

Ashton Clanfield Nicholas Rhodes

FTI Consulting Ed Westropp James Styles

+44 20 3727 1000

For further information on Pantheon Resources plc, see the website at:www.pantheonresources.com

In accordance with the AIM Rules - Note for Mining and Oil & Gas Companies - June 2009, the information contained in this announcement has been reviewed and signed off by Jay Cheatham, a qualified Chemical & Petroleum Engineer, who has over 40 years' relevant experience within the sector.

The information contained within this RNS is considered to be inside information prior to its release.

Neither the contents of the Company's website nor the contents of any website accessible from hyperlinks on the Company's website (or any other website) is incorporated into, or forms part of, this announcement.

Glossary

bopd

barrels of oil per day

bwpd

barrels of water per day

FTP

flowing tubing pressure

frac

fracture stimulation procedure

mcfpd

thousand cubic feet per day

Attachments

  • Original document
  • Permalink

Disclaimer

Pantheon Resources plc published this content on 09 April 2018 and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on 09 April 2018 07:50:09 UTC