At the beginning of May, the dismantled crane was delivered to Bremerhaven on 35 trucks over a period of three days. Working together, personnel from Schmidbauer and BLG assembled the individual parts within two days. The pressure applied by the crane to the ground depends on the configuration, the weight of the load, and the working radius. The load-carrying capacity of the ground was calculated in advance.

On May 6, BLG used the crawler crane to lift a 226-ton generator out of a barge. Just a few days later, a BLG SPMT transferred the generator onto a car carrier and it departed for Australia.

Handling of the 333-ton turbine is scheduled for the end of June. This will set a new weight record for BLG AutoTerminal Bremerhaven.