Xcel Energy Southwest Transmission Company, LLC announced Federal Energy Regulatory Commission issue the following Delegated Order. On May 10, 2024, the Commission issued a delegated order in the above-docketed proceeding. This errata serves as a correction to the Order, to replace the ordering paragraph 1, striking: This authorization is effective from May 13, 2024 through April 12, 2026 and replacing with: This authorization is effective from May 13, 2024 through May 12, 2026.

This Errata replaces the one issued March 20, 2026. Amery S. Poré, Director Division of Electric Power Regulation - West. Xcel Energy Southwest Transmission Company, LLC, 187 FERC ¶ 62,101 (2004) (Order).

Document Accession #: 20260323-3066 Filed Date: March 23, 2026. Document Content(s) ES24-30-000 Errata2.docx 1 Document Accession #: 20260323-3066 Filed Date: March 23, 2026.