Silver Storm Mining Ltd. reported that all eight new flotation cells have been fabricated and delivered to site at the Company's 100% owned La Parrilla Silver Mine Complex (the "La Parrilla Complex") in Durango, Mexico. The installation of the new 1,000 ft3 flotation cells, when combined with the existing processing equipment, will allow the processing capacity of the sulphide flotation circuit at the La Parrilla Complex to be expanded from 1,000 tpd to 1,250 tpd. Two of the new cells have already been installed, with the remaining six cells slated for installation during the first quarter of 2026.

Silver Storm is committed to advancing toward a potential near-term restart of its 100% owned La parrilla Silver Mine Complex, a tremendous operation comprised of a 2,000 tpd mill and three underground mines. The Company also holds a 100% interest in the San Diego Project, which is among the largest undeveloped silver assets in Mexico.