According to a statement, the projects are part of a broader 400 MW framework agreement, with the remaining capacity to be confirmed and announced as soon as it becomes definitive and unconditional.
The order includes the Andretta-Bisaccia project, which foresees the installation of five EnVentus V150 wind turbines of 5.6 MW each and twelve V150 turbines of 4.5 MW, as well as the Rocchetta project, which will feature the installation of four V136 turbines of 4.5 MW.
Both projects will be supported by a 10-year service and maintenance contract, ensuring optimal performance and reliability throughout their lifecycle.
The delivery and commissioning of the turbines are scheduled for the fourth quarter of 2026.
(Giancarlo Navach, editing by Gianluca Semeraro)