Outstanding Stage-2 construction involved completion of the site electrical substation, which primarily consisted of internal fit-out, drainage, sewage and landscaping. These works have now finished and this marks the completion of all works included in the Stage 2 construction scope by the appointed EPC contractor Metix (a wholly owned subsidiary of SMS group,
A formal handover inspection of the substation was conducted toward the end of
Stage 1 and 2 early works construction activities were completed with a total of 137,916 lost time injury (LTI) free hours at the site by the EPC construction team and its appointed subcontractors. A total of 288 personnel were involved in site-based construction activities.
To view the quarterly report, please visit:
https://abnnewswire.net/lnk/11K6TN03
About
HPA is a high-value, high margin and highly demanded product as it is the critical ingredient required for the production of synthetic sapphire. Synthetic sapphire is used in the manufacture of substrates for LED lights, semiconductor wafers used in the electronics industry, and scratch-resistant sapphire glass used for wristwatch faces, optical windows and smartphone components. There is no substitute for HPA in the manufacture of synthetic sapphire.
Global HPA demand is approximately 25,315tpa (2016) and demand is growing at a compound annual growth rate (CAGR) of 16.7% (2016-2024), primarily driven by the growth in worldwide adoption of LEDs. As an energy efficient, longer lasting and lower operating cost form of lighting, LED lighting is replacing the traditional incandescent bulbs.
Contact:
Corporate
Managing Director
Tel: +61-8-6168-1555
Email: info@altechchemicals.com
Company Secretary
Tel: +61-8-6168-1555
Email: info@altechchemicals.com
Investor Relations (
Tel: +49-69-175-548320
Email: hoffmann@soarfinancial.com
Copyright (C) 2020 ABN Newswire. All rights reserved., source