Trading Symbol: TSX-V: ARTG
All figures presented in Canadian Dollars, unless specified otherwise
As presented in the Company's consolidated financial statements, the Company reported a cash and cash equivalents balance of
The Company also provides the following update on activities regarding the development of the
- Early works construction at Blackwater remains targeted to commence in Q2 2022 to prepare the Project site in order to accommodate the commencement of major works construction activities.
- Artemis expects to award the Engineering Procurement and Construction ("EPC") contract to the successful bidder for the process plant by the end of
April 2022 . - The Company is now targeting receipt of the BC Mines Act Permit in Fall 2022 with major construction activities to commence shortly thereafter.
- The Project schedule maintains an estimated first gold pour date of H1 2024, consistent with the schedule outlined in the 2021 Feasibility Study technical report entitled "Blackwater Gold Project NI 43-101 Technical Report on Updated Feasibility Study" dated
September 10, 2021 " ("Feasibility Study")
Further updates will be provided in due course.
Qualified Person
On behalf of the Board of Directors,
On behalf of the Board of Directors
"
Chairman and Chief Executive Officer
Neither the
Cautionary Note Regarding Forward-Looking Information
This news release contains certain "forward looking statements" and certain "forward-looking information" as defined under applicable Canadian and
Forward-looking statements and information are not historical facts and are made as of the date of this news release. These forward-looking statements involve numerous risks and uncertainties and actual results may vary. Important factors that may cause actual results to vary include without limitation, risks related to the ability of the Company to accomplish its plans and objectives with respect to the Project within the expected timing or at all; the timing of the finalization of definitive documents related to the PLF and the satisfaction of other conditions precedent; the timing and receipt of certain approvals, changes in commodity and power prices, changes in interest and currency exchange rates, risks inherent in exploration estimates and results, timing and success, inaccurate geological and metallurgical assumptions (including with respect to the size, grade and recoverability of mineral reserves and resources), changes in development or mining plans due to changes in logistical, technical or other factors, unanticipated operational difficulties (including failure of plant, equipment or processes to operate in accordance with specifications, cost escalation, unavailability of materials, equipment and third party contractors, delays in the receipt of government approvals, industrial disturbances or other job action, and unanticipated events related to health, safety and environmental matters), political risk, social unrest, and changes in general economic conditions or conditions in the financial markets. In making the forward-looking statements in this news release, the Company has applied several material assumptions, including without limitation, the assumptions that: (1) market fundamentals will result in sustained mineral demand and prices; (2) the receipt of any necessary approvals and consents in connection with the development of any properties; (3) the availability of financing on suitable terms for the development, construction and continued operation of any mineral properties; and (4) sustained commodity prices such that any properties put into operation remain economically viable. The actual results or performance by the Company could differ materially from those expressed in, or implied by, any forward-looking statements relating to those matters. Accordingly, no assurances can be given that any of the events anticipated by the forward-looking statements will transpire or occur, or if any of them do so, what impact they will have on the results of operations or financial condition of the Company. Except as required by law, the Company is under no obligation, and expressly disclaims any obligation, to update, alter or otherwise revise any forward-looking statement, whether written or oral, that may be made from time to time, whether as a result of new information, future events or otherwise, except as may be required under applicable securities laws.