6 April 2022

For personal use only

Blackstone to Commence Ta Khoa Refinery Piloting

Feed Stocks Delivered and Ready for Piloting

Blackstone Minerals Limited ("Blackstone" or the "Company") is pleased to inform investors that key nickel and cobalt feed stocks for the Ta Khoa Refinery Piloting Program have been delivered to the ALS Metallurgical Laboratory in Balcatta Western Australia, and the contractor is in final preparation to commence piloting in April.

Key piloting preparation activities recently completed include:

  • Safe completion of 541m of underground development for the ongoing bulk sample project delivering 2,088t of disseminated sulfide (DSS) sample to the mill for processing

  • Successful restart and operation of the Ban Phuc nickel concentrator, and processing of 1,400t of DSS sample ore (refer Figure 1)

  • Delivery of 24.5t of samples to ALS Laboratories including:

    • o 7.5t of Ban Phuc sulfide flotation product

    • o 10t of sulfide flotation products from Trafigura

    • o 6t of sulfide flotation products from other third-party sources

    • o 1t of Cobalt Hydroxide (from Trafigura) as low-cost alternative to battery grade cobalt sulfate

  • Fabrication and installation of the Ta Khoa Upstream Pilot plant at Ban Phuc.

Figure 1 - Nickel Sulfide Flotation, operating at Ban Phuc

Level 5, 600 Murray Street, West Perth, Western Australia 6005 | PO Box 1175, West Perth WA 6872

T +61 8 9425 5217 | F +61 8 6500 9982 | Eadmin@blackstoneminerals.com.au| blackstoneminerals.com.au

Scott Williamson, Blackstone's Managing Director, said:

For personal use only

"The Ban Phuc mining, processing and maintenance teams have worked tirelessly to refurbish and recommission the Ban Phuc nickel concentrator. Blackstone is excited to commence the Ta Khoa piloting program with ALS, as we continue to de-risk the project.

"Blackstone is committed to sustainable mining and its development plans to recommence full commercial scale operations in Vietnam. As we progress further into pilot plant testing and feasibility studies, we will continue to advance our engagement and collaboration with potential partners and customers for our vertically integrated development strategy."

Mining Program

In December 2021, Blackstone was

granted approval to recommence

mining activities as part of our ongoing

development of the Ta Khoa Nickel

Project. Approval was received to

perform mining works that will involve

completion of ~1,000m of lateral

development (refer ASX announcement 9

December 2021).

To 29 March 2022, Blackstone had

successfully completed 541m of

development, delivering 2,088t of ore

to the surface, and averaging 136m a

month (refer Figure 2).

Figure 2 - In Progress Development Drive

Ban Phuc Nickel Concentrator

The existing 450ktpa Ban Phuc nickel concentrator was recommissioned in January 2022. Recommissioning works were completed by the skilled Ban Phuc operating and maintenance team, many of whom were part of the original team who operated the plant back in 2013-16. The plant was placed on care and maintenance in September 2016 and has been meticulously maintained. The efficiency of recommissioning activities, and successful operation of the crushing circuit (refer Figure 3) and concentrator, gives Blackstone great confidence in its suitability for treating regional massive sulfide vein (MSV) ore bodies. Blackstone has the optionality to turn on the Ban Phuc nickel concentrator and process MSV orebodies, particularly in an elevated nickel price environment.

Level 5, 600 Murray Street, West Perth, Western Australia 6005 | PO Box 1175, West Perth WA 6872

T +61 8 9425 5217 | F +61 8 6500 9982 | Eadmin@blackstoneminerals.com.au| blackstoneminerals.com.au

For personal use only

Figure 3 - Ban Phuc Secondary Crushing Circuit

Approximately 7.5t Ban Phuc flotation samples were packed and shipped to ALS Laboratories in Balcatta WA, ready for pilot program kick-off in April (refer Figure 4).

Figure 4 - Ban Phuc Flotation Samples

Piloting Program

The Main purpose of the piloting program is to replicate the full scale TKR flowsheet to confirm preliminary test work conditions and provide an insight into the operation conditions of the continuous plant. Evaluation of the pilot plant data will help to further develop engineering data required for the TKR design and close gaps from previous testwork.

The pilot plant program is broken up into two phases of the downstream refinery flowsheet: the Extraction Phase, and Refining Phase.

The Extraction Phase will consist of four campaigns of between seven to ten days and will cover the front end of the downstream refinery flowsheet entailing the feed concentrate handling/feed to POX up to the production of MHP. The focus of this campaign will be to

Level 5, 600 Murray Street, West Perth, Western Australia 6005 | PO Box 1175, West Perth WA 6872

T +61 8 9425 5217 | F +61 8 6500 9982 | Eadmin@blackstoneminerals.com.au| blackstoneminerals.com.au

test the design envelope for the POX Autoclave to maximise extraction of nickel, cobalt, and manganese.

For personal use only

The Refining Phase will focus on the second half of the flowsheet, including MHP Releach, electrolyte purification (SX), through to NCM Precursor precipitation and drying. The refining solvent extraction stages will be tested over a combined 34 days.

Figure 5 - Pilot Plant Autoclave

Authorised by the Managing Director on behalf of the Board.

For more information, please contact

Scott Williamson

Dhanu Anandarasa

Patrick Chang

Managing Director

Manager Corporate Development

Executive

+61 8 9425 5217

+61 8 9425 5217

+61 8 9425 5217

scott@blackstoneminerals.com.au

dhanu@blackstoneminerals.com.au

patrick@blackstoneminerals.com.au

Level 5, 600 Murray Street, West Perth, Western Australia 6005 | PO Box 1175, West Perth WA 6872

T +61 8 9425 5217 | F +61 8 6500 9982 | Eadmin@blackstoneminerals.com.au| blackstoneminerals.com.au

About Blackstone

For personal use only

Blackstone Minerals Ltd (ASX: BSX / OTCQX: BLSTF / FRA: B9S) is focused on building an integrated upstream and downstream battery metals processing business in Vietnam that produces NCM Precursor products for Asia's growing Lithium-ion battery industry.

The Company owns a 90% interest in the Ta Khoa Nickel Project (TKNP). The TKNP is located 160km west of Hanoi in the Son La Province of Vietnam (refer Figure 6) and includes an existing modern nickel mine built to Australian standards, which is currently being used to process nickel ore delivered by the underground bulk sample program. The Ban Phuc nickel mine successfully operated as a mechanised underground nickel mine from 2013 to 2016.

Blackstone's TKNP and Ta Khoa Refinery (TKR) are the two major cogs in Blackstone's vertically integrated development strategy (together the Ta Khoa Project). The Company's development strategy is underpinned by Blackstone's ability to secure nickel concentrate and Ta Khoa is emerging as a nickel sulfide district of enviable scale with several exploration targets yet to be tested.

In February 2022, Blackstone completed a Pre-Feasibility Study for the TKNP, and presented this on an integrated basis with the proposed TKR development (refer ASX announcement 28 February 2022). The TKR is being designed to have a refining capacity of 400ktpa, with feedstock provided from a combination of concentrate from the TKNP and third-party feed sources (3PF). Pilot Plant testing and Definitive Feasibility Studies are underway and will continue to technically de-risk the Ta Khoa Project.

At both the mine (upstream) and refinery (downstream) level, Blackstone is focused on a partnership model and is collaborating with groups who are focused on sustainable mining, minimising carbon footprint and implementing a fully vertically integrated supply chain.

Level 5, 600 Murray Street, West Perth, Western Australia 6005 | PO Box 1175, West Perth WA 6872

T +61 8 9425 5217 | F +61 8 6500 9982 | Eadmin@blackstoneminerals.com.au| blackstoneminerals.com.au

This is an excerpt of the original content. To continue reading it, access the original document here.