The 15-year contract to supply 750,000 tonnes of liquefied natural gas per year doubles the initial commitment by
Woodfibre spokeswoman
She says Woodfibre LNG is currently undergoing final engineering work while attempting to amend its environmental permit to allow floating accommodation for up to 600 workers during construction.
Scott says housing workers on barges is being considered after consultations with the community, as a partial solution to the high prices and low availability of housing on land near the site, a former pulp and paper mill located halfway between
At one time, about 20 LNG terminals were proposed for the
“Forward-looking companies like BP are turning to projects like ours for sustainable, stable gas that will supply a clean energy mix,” said
“We look forward to working with BPGM to deliver Canadian natural gas from one of the lowest carbon footprint LNG facilities in the world, and help advance the climate goals of growing economies as they phase away from coal, lower their emissions, and meet net-zero targets.”
Work on the LNG project was delayed more than a year ago after the main engineering, procurement and construction contractor, McDermott, filed for Chapter 11 bankruptcy protection in
McDermott has since emerged from the court process to continue its contract with Woodfibre, Scott said.
This report by