Calidus Resources declared commercial production at the Warrawoona Gold Project (WGP). The processing plant is now operating at nameplate capacity. A total of 191,000t @ 0.85g/t was processed in December with 5,053 ozs of gold produced.

The operation averaged 235oz recovered per day for the last third of the month. Estimated, unaudited cash costs for December were approximately AUD 2,050/oz.