Century Extrusions Limited at its board meeting held on July 10, 2024, announced that it is planning to set up new Extrusion Press at existing plant located in Kharagpur, aimed at enhancing its production capacity and operational efficiency. Location: Kharagpur Factory. Installed Capacity: 9000 tonnes (approximately).

Investment: INR 200 million. Timeline: Installation to be completed within 12 months. Operational Efficiency: Modern equipment will streamline manufacturing processes, reduce downtime, and enhance overall operational efficiency, thereby optimizing resource utilization.

Implementation Plan: Phase 1 (Months 1-6): Procurement and delivery of Press components, site preparation, and initial setup. Phase 2 (Months 7-12): Installation, testing, commissioning, and finalization of operational processes.