Information on parameters at Unit 1:

  • Unit is in the operation
  • Turbine generator output - 1079 MWe
  • Electricity production since the beginning of the year: 5 376 507 MWh

Information on parameters at Unit 2:

  • Unit is in the operation
  • Turbine generator output - 1089 MWe
  • Electricity production since the beginning of the year: 5 215 846 MWh

Attachments

  • Original document
  • Permalink

Disclaimer

CEZ a.s. published this content on 23 September 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 23 September 2021 11:21:05 UTC.