Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 500 MWe
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 498 MWe
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 495 MWe
Unit 4 is in Mode 6 - outage

Electricity production since the beginning of the year: 1 855 949 MWh.

Jiří Bezděk , Spokesman of the ČEZ Group, Nuclear Power Plant Dukovany

Attachments

  • Original document
  • Permalink

Disclaimer

CEZ a.s. published this content on 22 February 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 22 February 2021 06:29:01 UTC.