Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 7 - outage
Unit 2 is in Mode 1 - startup after refuelling, Reactor power is 92,4 %, Turbine generator output - 458 MWe
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 493 MWe
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 503 MWe

Electricity production since the beginning of the year: 13 057 230 MWh.