Information on parameters of Unit 1-4, today at 7:00 hrs:
Unit 1 is in Mode 6 - outage
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 502 MWe
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 497 MWe
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 500 MWe
Electricity production since the beginning of the year: 967 060 MWh.
Jiří Bezděk , Spokesman of the ČEZ Group, Nuclear Power Plant Dukovany