Information on parameters of Unit 1-4, today at 7:00 hrs:

Unit 1 is in Mode 6 - outage
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 502 MWe
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 497 MWe
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 500 MWe

Electricity production since the beginning of the year: 967 060 MWh.

Jiří Bezděk , Spokesman of the ČEZ Group, Nuclear Power Plant Dukovany

Attachments

  • Original document
  • Permalink

Disclaimer

CEZ a.s. published this content on 28 January 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 28 January 2021 06:45:01 UTC.