Information on parameters of Unit 1-4, today at 7:00 hrs:
Unit 1 is in Mode 7 - outage
Unit 2 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 501 MWe
Unit 3 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 493 MWe
Unit 4 is in Mode 1 - power operation, Reactor power is 100 %, Turbine generator output - 500 MWe
Electricity production since the beginning of the year: 13 297 621 MWh.
Jiří Bezděk , Spokesman of the ČEZ Group, Nuclear Power Plant Dukovany
Attachments
- Original document
- Permalink
Disclaimer
CEZ a.s. published this content on 04 December 2020 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 04 December 2020 06:28:01 UTC