Copel Completes Acquisition of Aventura and

Santa Rosa & Mundo Novo Wind Farms

COPEL ("Company"), a company that generates, transmits, distributes and trades energy, informs its shareholders and the market in general that pursuant to Material Fact 02/22, of October 6, 2022, and after complying with the condition's precedent, concluded on this date the acquisition of the Aventura and Santa Rosa & Mundo Novo Wind Complexes ("Project" or "Complex"), in the updated value (Enterprise Value) of R$1,760.6 million.

The Project has long-term financing (maturities up to 2043) contracted with Banco do Nordeste (BNB), with rates of IPCA + 2.19% p.a. (Adventure Complex) and IPCA + 1.98% p.a. (Santa Rosa & Mundo Novo complex).

Wind Farms Installed Capacity (MW)1 Assured Energy (MWmed) Commercial Operation Energy Trade - Regulated Contracting Enviroment (ACR) End of Authorization
Auction Quantity (MWmed) Price (R$/MWh)2 Start of Supply End of Supply
Aventura II 105 65 In operation (jul/21) A-6
2017
53.6 128.29 jan/23 dec/42 2053
Aventura III
Aventura IV
Aventura V
SRMN I 155.4 92.8 In operation (dez/21 to fev/22) A-6
2017
67.1 130.94 jan/23 dec/42 2053
SRMN II
SRMN III
SRMN IV 2052
SRMN V
Total/Average 260.4 157.8 - 120.7 129.76
1 Total of 62 wind turbines used in the project, manufacturer Vestas model V 150.
2 Base date Jan/2023

With the addition of this capacity, the wind source now represents 17% of the Copel Group's energy generation portfolio, benefiting its portfolio with the increase in incentivized energy and the reduction of exposure to hydrological risk.

The completion of the acquisition process for this project is another important step in the implementation of the Company's strategy of sustainable growth in renewable energy, expanding the diversification of the generation matrix in line with the Strategic Planning and Investment Policy.

Curitiba, January 30, 2023.

Adriano Rudek de Moura

Chief Financial and Investor Relations Officer

For further information, please contact the Investor Relations team:

ri@copel.com or +55 41 3331-4011