Construction Started

Australia's Newest

Lithium Producer

AGM Presentation

25th November 2021

Important and Cautionary Notes

ersonal use only

This presentation has been prepared by Core Lithium Ltd ("Core", "Company") and provides a general overview of the Company and its strategy. This presentation does not purport to be all-inclusive or to contain all the information that you or any other party may require to evaluate the prospects of the Company. None of the Company, any of its related bodies corporate or any of their representatives assume any responsibility for, or makes any representation or warranty, express or implied, with respect to the accuracy, reliability or completeness of the information contained in this presentation and none of those parties have or assume any obligation to provide any additional information or to update this presentation.

To the fullest extent permitted by law, the Company, its related bodies corporate and their representatives expressly disclaim liability for any loss or damage arising in respect of your reliance on the information contained in this presentation (including your reliance on the accuracy, completeness or reliability of that information), or any errors in or omissions from this presentation, including any liability arising from negligence. The Finniss Lithium Project as described in this presentation is at the pre-development stage, and potential investors should understand that mineral exploration and development are high- risk undertakings. There is no guarantee that the Finniss Lithium Project can be economically exploited.

This document contains statements which may be in the nature of forward-looking statements. No representation or warranty is given, and nothing in this presentation or any other information made available by the Company or any other party should be relied upon as a promise or representation, as to the future condition of the respective businesses and operations of the Company.

Competent Person Statements

The information in this release that relates to the estimation and reporting of Ore Reserves and Mineral Resources for the Grants deposit for the Finniss Project was first reported by the Company on 26 July 2021. The information in this release that relates to the estimation and reporting of Mineral Resources for the Finniss Project (other than the Grants deposit) was first reported by the Company on 15 June 2020. The information in this release that relates to production targets and forecast financial information for the Finniss Project was first reported by the Company on 26 July 2021. The information in this release that relates to exploration targets for the Finniss Project was first reported by the Company on 20 May 2021. Core confirms that it is not aware of any new information or data that materially affects the information included in those announcements and that all material assumptions and technical parameters underpinning the exploration targets, Mineral Resource estimates, Ore Reserve estimates, production targets and forecast financial information in those announcements (as applicable) continue to apply and have not materially changed, save for the Mineral Resources estimates of the Grants deposit reported by the Company on 15 June 2020 which has been updated by the 26 July 2021 release.

Forward‐looking Statements

This release contains "forward-looking information" that is based on the Company's expectations, estimates and projections as of the date on which the statements were made. This forward-looking information includes, among other things, statements with respect to the scoping, pre-feasibility and feasibility studies, the Company's business strategy, plan, development, objectives, performance, outlook, growth, cash flow, projections, targets and expectations, and Mineral Resources and Reserves. Generally, this forward-looking information can be identified by the use of forward-looking terminology such as 'outlook', 'anticipate', 'project', 'target', 'likely',' believe', 'estimate', 'expect', 'intend', 'may', 'would', 'could', 'should', 'scheduled', 'will', 'plan', 'forecast', 'evolve' and similar expressions. Persons reading this news release are cautioned that such statements are only predictions, and that the Company's actual future results or performance may be materially different. Forward-looking information is subject to known and unknown risks, uncertainties and other factors that may cause the Company's actual results, level of activity, performance or achievements to be materially different from those expressed or implied by such forward-looking information. Forward-looking information is developed based on assumptions about such risks, uncertainties and other factors set out herein, including but not limited to general business, economic, competitive, political and social uncertainties; the actual results of current exploration activities; conclusions of economic evaluations; changes in project parameters as plans continue to be refined; future prices of lithium; possible variations of ore grade or recovery rates; failure of plant, equipment or processes to operate as anticipated; accident, labour disputes and other risks of the mining industry; and delays in obtaining governmental approvals or financing or in the completion of development or construction activities. This list is not exhaustive of the factors that may affect our forward-looking information. These and other factors should be considered carefully, and readers should not place undue reliance on such forward-looking information. The Company disclaims any intent or obligations to or revise any forward-looking statements whether as a result of new information, estimates, or options, future events or results or otherwise, unless required to do so by law. Statements regarding plans with respect to the Company's mineral properties may contain forward-looking statements in relation to future matters that can be only made where the Company has a reasonable basis for making those statements.

Currency

Unless otherwise stated, all cashflows are in Australian dollars, are undiscounted and are in real terms (not subject to inflation/escalation factors), and all years are calendar years. C1 Operating Costs and All-In Sustaining Cost (AISC) references in USD throughout this presentation have been derived by converting AUD using an exchange rate of 0.70 AUD/USD.

2

Construction started on Australia's newest lithium mine

ersonal use only

Construction underway on Core's 100%-owned Finniss Lithium Project

  • Site construction and establishment works are now underway
  • Construction follows Final Investment Decision (FID) in Sep21
    • Mining Contract executed (Lucas) - mining starting during the current quarter (Q4 2021)
    • EPC Contract executed (Primero) - DMS plant construction commencing March 2022
  • First production of lithium concentrate scheduled Q4 2022
  • Core the only Australian company forecast to initiate new Australian lithium production in 2022
  • Project development is fully funded with $150m financing completed

3

ersonal use only

Construction started on Australia's newest lithium mine

4

ersonal use only

Construction started on Australia's newest lithium mine

5

This is an excerpt of the original content. To continue reading it, access the original document here.