Finniss Project Development Update

Highlights

  • Development earthworks are on schedule, with the establishment of access roads and water pipelines, while water management infrastructure, administration areas and communication facilities are well advanced

  • Earthworks for the DMS plant pad is due for completion in April 2022

  • Construction of the DMS plant set to commence immediately after pad completion

  • First production continues to be anticipated prior to the end of calendar year 2022

Australia's next lithium producer, Core Lithium Ltd (Core or Company) (ASX: CXO), is pleased to provide an update on development activities at its Finniss Lithium Project near Darwin in the Northern Territory.

To date, the majority of the activity undertaken on site has been preparatory infrastructure works needed to support the mining and plant construction efforts. Activities have included road works, clearing, establishment of administration buildings and erection of communication towers.

The water management Infrastructure works have seen the completion and commissioning of the 7km process water pipeline from Observation Hill Dam, the commencement of construction of the drainage control infrastructure, and the commencement of construction of the erosion and sediment control infrastructure.

The dense media separation (DMS) process plant pad, which is due for completion in April 2022, will pave the way for Primero Group to commence plant construction activities. Primero are well advanced with the design of the plant and all long lead packages ordered. They have achieved access to site and personnel in the Northern Territory ready to start work.

Development of the Finniss Lithium Project continues to run according to schedule, and the Company looks forward to seeing the next stages of site work at Finniss proceed during the dry season.

With the wet season approaching its end in April, Core expects site activities to focus on the pre-strip needed to uncover ore by about mid-year and the erection of the DMS plant.

Figure 1. Steel wall framing of the Finniss site administration office complex

Figure 2. Earthworks underway at the Finniss Project

Figure 3. Liebherr R 9200 excavator arrives on site at the Finniss Project

Core Managing Director Stephen Biggins said:

"It is incredibly pleasing to see the foundations of the Finniss Project come to life and begin to take shape in Darwin.

"As the end of the wet season approaches, we look forward to seeing site activities significantly ramp up, with our path to first production before the end of 2022 firmly on-track."

Figure 4. CAT777 truck being loaded at the Finniss Lithium Project

Figure 5. Core's thriving cycads following their relocation

This announcement has been approved for release by the Core Lithium Board.

For further information please contact:

For Media and Broker queries:

Stephen Biggins

Fraser Beattie

Managing Director

Account Manager

Core Lithium Limited

Cannings Purple

+61 8 8317 1700

+61 421 505 557

info@corelithium.com.au

fbeattie@canningspurple.com.au

This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original Link
  • Original Document
  • Permalink

Disclaimer

Core Lithium Ltd. published this content on 03 April 2022 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 03 April 2022 23:13:05 UTC.