FIXED INCOME INVESTOR PRESENTATION
1 Q 2 1 | R E S U L T S
Visão
ISA CTEEP geral
Sustainable Value
Financial Highlights
Madeira (51%) | |
LT: 2.4 thousand km | |
ISA CTEEP | Substation: 7.5 thousand MVA |
RAP2020/2021 cycle¹: BRL282 million | |
Largest publicly traded pure transmission utility in Brazil
Transmission of 33% of Brazil's energy generation and 94% of the energy in the State of São Paulo
Benchmark player in costs and quality
Aguapeí³(100%) | |||||||||||||||||
LT: 121 km | |||||||||||||||||
OPERATIONAL | Substation: 1.400 MVA | ||||||||||||||||
RAP 2020/2021 cycle: BRL60 million | |||||||||||||||||
ASSETS | |||||||||||||||||
Itapura - Bauru (100%) | |||||||||||||||||
Static Compensator: 250 MVAr | |||||||||||||||||
18.8 thousand km of transmission lines | RAP 2020/2021 cycle: BRL12 million | ||||||||||||||||
Pinheiros (100%) | |||||||||||||||||
69 thousand MVA of transformation | |||||||||||||||||
Substation: 4.2 thousand MVA | |||||||||||||||||
capacity | LT: 1 km | ||||||||||||||||
RAP 2020/2021 cycle: BRL63 million | |||||||||||||||||
129 substations | |||||||||||||||||
Transmission Line (LT) | Serra do Japi (100%) | ||||||||||||||||
LT: 137 km | |||||||||||||||||
RAP of BRL4 billions¹ | Consolidated subsidiary | Substation: 2 thousand MVA | |||||||||||||||
RAP 2020/2021 cycle: BRL56 million | |||||||||||||||||
LT consolidated subsidiary | |||||||||||||||||
Non-consolidated subsidiary | IESUL (100%) | ||||||||||||||||
LT: 167 km | |||||||||||||||||
Note: | |||||||||||||||||
LT non-consolidated subsidiary | Substation: 900 MVA | ||||||||||||||||
¹ RAP 2020/2021 cycle adjusted to ISA CTEEP's participation | |||||||||||||||||
2 | IE Tibagi's RAP does not consider adjustment resulting from the | RAP 2020/2021 cycle: BRL20 million | |||||||||||||||
contractual amendment (-13.5%), approved by ANEEL's Board on 10/26/20 |
IENNE (100%)
LT: 710 km
Substation: N/A
RAP 2020/2021 cycle: BRL53 million
Garanhuns (51%)
LT: 633 km
Subestation: 2.1 thousand MVA
RAP 2020/2021 cycle: BRL48 million
Evrecy (100%)
LT: 163 km
Subestation: 450 MVA
RAP 2020/2021 cycle: BRL13 million
IEMG (100%)
LT: 173 km
Substation: N/A
RAP 2020/2021 cycle: BRL20 million
ISA CTEEP | PBTE (100%) |
LT: 14,3 mil km | LT: 30 km |
Substation : 48,8 mil MVA | Substation: N/A |
RAP 2020/2021 cycle: BRL3.1 billion | RAP 2020/2021 cycle: BRL172 |
Itaquerê (100%) | million |
Synchronous Components: 900 | |
MVAr | |
RAP 2020/2021 cycle: BRL52 million | |
Tibagi² (100%) | |
LT: 17 km | |
Substation : 500 MVA | |
RAP 2020/2021 cycle: BRL21 million |
PROJECTS
UNDER CONSTRUCTION
Paraguaçu (50%)
LT: 338 km
Substation: N/A
CAPEX ANEEL: BRL255 million
RAP 2020/2021 cycle: BRL61 million
Deadline ANEEL: Fev/22
Triângulo Mineiro (100%)
LT: 172 km
Substation: 1.6 thousand MVA
CAPEX ANEEL: BRL554 million
RAP 2020/2021 cycle: BRL33 million
Deadline ANEEL: Dec/24
Organic growth: average CAPEX of BRL220 million/year with average RAP of
BRL45 million/year
1.7 thousand km of transmission lines¹
9 thousand MVA of transformation capacity¹
CAPEX ANEEL of BRL6.3 billion
Ivaí (50%) LT: 600 km
Substation: 3 thousand MVA
CAPEX ANEEL : BRL968 million
RAP 2020/2021 cycle: BRL150 million Deadline ANEEL: Aug/22
Três Lagoas (100%)
LT: 37 km
Substation: N/A
CAPEX ANEEL: BRL99 million RAP 2020/2021 cycle: BRL5 million Deadline ANEEL: Jun/23
Aimorés (50%) LT: 208 km Substation: N/A
CAPEX ANEEL: BRL171 million
RAP 2020/2021 cycle: BRL41 million
Deadline ANEEL: Feb/22
Itaúnas (100%)
LT: 79 km
Substation: 1.3 thousand MVA
1 Static Compensator
CAPEX ANEEL: BRL298 million
RAP 2020/2021 cycle: BRL53 million
Deadline ANEEL: Feb/22
Itapura - Lorena (100%)
LT: 5 km
Substation: 1.2 thousand MVA
RAP of BRL501 million²
Notes:
¹ Considers project information (100%)
² RAP 2020/2021 cycle adjusted to ISA CTEEP's participation
Minuano (100% ) | Biguaçú (100%) |
LT: 169 km | |
Substation: 800 MVA | LT: 27 km |
CAPEX ANEEL : BRL682 million | Substation: 300 MVA |
RAP 2020/2021 cycle: BRL38 million | CAPEX ANEEL: BRL641 million |
Deadline ANEEL: Dec/24 | RAP 2020/2021 cycle: BRL41 million |
Deadline ANEEL: Sept/23 |
Subsidiaries
Consolidated subsidiary
Non-consolidated subsidiary
CAPEX ANEEL: BRL238 million
RAP 2020/2021 cycle: BRL11 million
Deadline ANEEL: Sept/22
Riacho Grande (100%) LT: 31 km
Substation: 800 MVA
CAPEX ANEEL: BRL1 billion
RAP 2020/2021 cycle: BRL68 million
Deadline Aneel: Dec/25
Corporate Governance Structure
Shareholders
Board of Directors
8 effective members. of which 2 are independent and one is elected by the employees
Fiscal Council
5 effective members
and 5 substitute
members
Ethics and
Transparency
recognized at ISA
and at ISA CTEEP level
Experienced
Human Resources | Audit |
Committee | Committee |
CEO
Rui Chammas
CFO and IRO | Chief Project Officer | Chief Strategy and Business | COO |
Development Officer | |||
Alessandro Gregori Filho | Dayron Urrego | Silvia Wada | Gabriela Desiré |
Management
team focused
on value creation
2020
Transparency
Trophy from
ANEFAC
This is an excerpt of the original content. To continue reading it, access the original document here.