Eltel Finland has signed two agreements with OX2 to build a new 400 kV transmission line as well as a 110 kV transmission line for the new Lestij?rvi wind farm in central Finland. The contracts have a combined value of about EUR 22 million. The Lestij?rvi wind farm will be the largest wind farm in Finland with 69 turbines and a total capacity of about 455 MW. The wind farm will have an estimated yearly output of about 1,3TWh, which corresponds to about 2% of the total annual electricity production in Finland. Eltel will contribute to the renewable and sustainable energy solution and bring expertise as the project proceeds. Eltel's scope of works covers turnkey delivery of two projects. One project comprises 58 km of 400 kV transmission line to connect Lestij?rvi wind farm to the national grid. The second project comprises 24 km of 110 kV transmission line within the wind park. The project will start in first quarter of 2022 and is scheduled to be completed early 2025.