Endeavour Silver Corp. announce the commencement of wet commissioning activities at its Terronera Project in Jalisco state, Mexico; a critical milestone in the lead-up to full-scale production. Terronera?s wet commissioning process involves the introduction of water and slurry into the plant circuits in order to validate the performance of equipment and systems under operational conditions.
This critical phase follows the successful completion of dry commissioning, during which the mechanical, electrical, and control systems are tested without load. The first slurry has now been introduced to the concentrate filter and preliminary performance has been consistent with design expectations. The operations and commissioning teams continue to closely monitor system performance, working in alignment with safety, environmental, and quality standards.
As the wet commission phase is completed, attention will be given to increasing feed and run times, and ramping up production to full throughput.