Energean plc announce that the Energean Power FPSO has arrived on location in Israel. The FPSO was transported by two tugs from Sembcorp Marine's Admiralty Yard in Singapore to Israel. The 5,532 nautical mile-long journey took 35 days, crossing six seas and passing through the Suez Canal.

Energean will immediately commence hook-up and commissioning operations, which includes risers and jumpers installation as well as the commissioning of the sales gas pipeline. Energean expects approximately three - four months of commissioning before first gas, which remains on track for Third Quarter this year.