Enertime obtained an order in 2016 under a contract signed between a companies consortium, including Enertime and the Ukrainian companies Kriger and UTEM with the customer 'Miskteplovodenerhiya', for the turnkey supply of a cogeneration plant Biomass of 1,6Mwe.

As part of this contract, ENERTIME carried out a site visit from 28 to 30 June. Marine Chambon, Enertime Biomass Project Engineer, declares: 'The construction site is progressing well and will be ready for the ORC module delivery at the beginning of August 2017'. The project, funded by the European Bank for Reconstruction and Development (EBRD), consists of installing and commissioning a biomass cogeneration plant composed of two biomass boilers of 5 and 10 MWth and an organic fluid machine Rankine cycle (ORC), to supply the urban heat network of the city of Kamyanets-Podilskyi in Ukraine.

Enertime SA published this content on 10 July 2017 and is solely responsible for the information contained herein.
Distributed by Public, unedited and unaltered, on 10 July 2017 16:04:18 UTC.

Original documenthttp://www.enertime.com/en/news/2017-07-10-enertime-a-effectue-une-visite-de-chantier-dans-le-cadre-du-contrat-signe-avec-les

Public permalinkhttp://www.publicnow.com/view/AC763391182415EAD16F76072735B5829741E73A