Accordingly, the Zainskaya 850 MW CCPP project, turnkey construction of which is undertaken by ENKA in Zainsk, Russia, will be the most efficient power plant in the Russian Federation when completed. The project will be based on 1x1x1 configuration, equipped with one GE's 9HA.02 Gas Turbine, one D650 Steam Turbine and one triple pressure reheat Heat Recovery Steam Generator (HRSG).
Attachments
- Original document
- Permalink
Disclaimer
Enka Insaat ve Sanayi AS published this content on 22 January 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 22 January 2021 07:47:08 UTC