Eurasia Mining PLC provided an update on its operations at West Kytlim. Due to delays and inconsistencies by the original contractor at West Kytlim only 66kg (2,122 oz) of platinum has been approved by authorities as the maximum approved production limit for production in 2019, thus only this volume of platinum could be produced. The amounts of the other metals (palladium, iridium, rhodium and gold) remain to be tallied and are to be finalised with the revenue from the Refinery for these metals payable on schedule by the end of this year. Further updates on this will be provided as appropriate. The state approval on the second Kluchiki deposit reserves calculation as well as definitive feasibility study was received as expected, with final confirmation received as official board meeting minutes from the Urals Reserves commission on 13th September 2019. These previously announced additional reserves at the Kluchiki area are now fully permitted for mining. Metal grades and stripping ratio in the 2019 season were on the same level as in the 2018 season. The production volumes were impacted by the approved production limit due to the late start caused by a few delays by the original contractor, speeding up the decision to shift from contractor operation to Eurasia's own operation. The Company continued mining at site until all reserves the above mentioned approved by the state for mining for the 2019 season had been mined out. To ensure sufficient available mineable material for the 2020 season the Company has taken measures to ensure the Bolshaya Sosnovka area will be available for mining. This area contains reserves previously approved as 748Kg (c. 24,000 oz) Raw Platinum. A drilling program of 682.5m, inclusive of 192m of larger diameter verification drilling was completed at this area during 2019 and was designed to bring these reserves to mineable status with approval to be sought over the winter period in accordance with the applicable laws. This should allow the Company to start mining at Kluchiki, and enable it to stockpile the ore until such time as the processing season starts (with the processing anticipated to start in March 2020). Mining at Bolshaya Sosnkova should commence thereafter. The Kluchiki reserves which are already available are in addition to those at the Bolshaya Sosnovka area. Eurasia is fully financed to start the 2020 season without contractors using its own equipment keeping all margins and positive effects from PGM prices. Finally, as previously announced the necessary gravel washing equipment and peripherals were purchased during the 2019 season. Further equipment including excavators, trucks and bulldozers were leased to maintain steady state delivery of ore to the washplant. Discussions with leasing companies and banks are now progressing at subsidiary level, to establish the best means of capitalising the necessary machinery for the 2020 season and beyond. Eurasia is on schedule to start mining in January 2020 to stockpile the ore for enrichment going forward once the processing season starts.