Alcoa is a global industry leader in the production of bauxite, alumina and aluminium, a position enhanced by a portfolio of value-added cast and rolled products and select energy assets. Since developing the aluminium industry more than 130 years ago, Alcoa has built a legacy of breakthrough innovations and best practices that have led to efficiency, safety, sustainability and stronger communities wherever they operate. Alcoa of Australia Limited is owned 60 per cent by Alcoa Corporation and 40 per cent by Alumina Limited. The Australian operations represent one of the world's largest integrated bauxite mining, alumina refining and aluminium smelting systems and add value to Australia's local, state and national economies at every stage.

The conditions precedent cover further HPA pilot plant variability trials being successful and the continued cooperation having commercial benefits for both parties. FYI is developing an innovative process for the production of high quality, high purity alumina. FYI has been very successful in its development strategy and continues to advance the HPA refining process to address the supply shortfalls in the rapidly growing HPA market. The MOU will allow the parties to explore and develop respective technical capabilities and capacities in alumina production, with the potential to leverage opportunities in the HPA market.

Future Value Catalysts The Updated DFS confirms the robustness and quality of FYI's HPA Project. Further to the Updated DFS results, there remains additional technical improvements and other commercial opportunities within FYI's HPA strategy which have not been incorporated into the updated DFS. These added opportunities may have the ability to positively impact on the Company's future valuation. These events include:

- Entering into a Joint Venture Agreement with Alcoa

- Additional process flowsheet development and demonstration

- Completion of HPA Project detailed engineering, front end engineering and final investment decision

- Continued product market qualification

- Signing of customer MOU's and strengthening marketing relationships

- Advancing financing arrangements

- Investigation of additional internal revenue streams

- Investigation into broader battery HPA utilisation and markets

- New demand growth sectors in HPA appearing through development channels.

This announcement regarding the Updated DFS should be read in conjunction with the initial DFS announcement of 11 March 2020.

Authorised for release by Roland Hill, Managing Director.

For more information please contact:


Roland Hill                      Simon Hinsley 
Managing Director                Investor & Media Relations 
Tel: +61 414 666 178             Tel: 0401 809 653 
roland.hill@fyiresources.com.au  simon@nwrcommunications.com.au 

Cautionary Statements

Substance of DFS and Updated DFS

The initial DFS and Updated DFS referred to in this announcement is a study of the potential viability of the production of high purity alumina from feedstock form the Cadoux Kaolin Project. It has been undertaken to understand the technical and economic viability of the Project.

The initial DFS and Updated DFS assumes as a 25-year Project life based only on Proved and Probable Ore Reserves (100%). The initial DFS and Updated DFS is based on the material assumptions set out in the initial DFS announcement of 11 March 2020 and updated assumptions set out in this announcement. These include assumptions about the availability of funding. While the Company considers all of the material assumptions to be based on reasonable grounds, there is no certainty that they will prove to be correct or that the range of outcomes indicated by the feasibility studies will be achieved.

To achieve the range of outcomes indicated in Updated DFS, funding in the order of AUSD202 million will likely be required. Investors should note that there is no certainty that the Company will be able to raise the amount of funding when needed. It is also possible that such funding may only be available on terms that may be dilutive to or otherwise affect the value of the Company's existing shares. It is also possible that the Company could pursue other "value realisation" strategies such as a sale, partial sale or joint venture of the Project. If it does, this could materially reduce the Company's proportionate ownership of the Project.

General and forward-looking statements The contents of this announcement reflect various technical and economic conditions, assumptions and contingencies which are based on interpretations of current market conditions at the time of writing. Given the nature of the resources industry, these conditions can change significantly and without notice over relatively short periods of time. Consequently, actual results may vary from those detailed in this announcement.

Some statements in this announcement regarding estimates or future events are forward-looking statements. They include indications of, and guidance on, future earnings, cash flow, costs and financial performance. Such forward-looking statements are provided as a general guide only and should not be relied on as a guarantee of future performance. When used in this announcement, words such as, but are not limited to, "could", "planned", "estimated", "expect", "intend", "may", "potential", "should", "projected", "scheduled", "anticipates", "believes", "predict", "foresee", "proposed", "aim", "target", "opportunity", "nominal", "conceptual" and similar expressions are forward-looking statements.

Although the Company believes that the expectations reflected in these forward-looking statements are reasonable, such statements involve risks and uncertainties, and no assurance can be given that actual results will be consistent with these forward-looking statements.

The contents of this release are also subject to significant risks and uncertainties that include but are not limited those inherent in mine development and production, geological, mining, metallurgical and processing technical problems, the inability to obtain and maintain mine licences, permits and other regulatory approvals required in connection with mining and processing operations, competition for among other things, capital, acquisitions of reserves, undeveloped lands and skilled personnel, incorrect assessments of the value of projects and acquisitions, changes in commodity prices and exchange rates, currency and interest rate fluctuations and other adverse economic conditions, the potential inability to market and sell products, various events which could disrupt operations and/or the transportation of mineral products, including labour stoppages and severe weather conditions, the demand for and availability of transportation services, environmental, native title, heritage, taxation and other legal problems, the potential inability to secure adequate financing and management's potential inability to anticipate and manage the foregoing factors and risks.

All persons should consider seeking appropriate professional legal, financial and taxation advice in reviewing this announcement and all other information with respect to the Company and evaluating the business, financial performance and operations of the Company. Neither the provision of this announcement nor any information contained in this announcement or subsequently communicated to any person in connection with this announcement is, or should be taken as, constituting the giving of investment or financial advice to any person. This announcement does not take into account the individual investment objective, financial or tax situation or particular needs of any person.

Competent Persons Statements

Ore Reserves The information in this announcement that relates to Ore Reserves is based on information compiled by Mr. Steve Craig, who is a Fellow of the Australasian Institute of Mining and Metallurgy. Steve Craig is a full-time employee of Orelogy Consulting Pty Ltd and has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which they are undertaking to qualify as a Competent Person as defined in the 2012 Edition of the "Australasian Code for Reporting of Exploration Results, Mineral Resources and Ore Reserves". The information is extracted from the Ore Reserve announcement released 29 October 2018 and the DFS announcement released 11 March 2020 and are available to view on the Company's website at www.fyiresources.com.au . The Company confirms that it is not aware of any new information or data that materially affects the information included in the original announcement and that all material assumptions and technical parameters underpinning the estimates in the relevant market announcements continue to apply and have not materially changed. The Company confirms that the form and context in which the Competent Person's findings are presented have not been materially modified from the original announcements.

Mineral Resources The information in this report that relates to Mineral Resources is based on information compiled by Mr Grant Louw, under the direction and supervision of Dr Andrew Scogings, who are both full-time employees of CSA Global. Dr Scogings is a Member of the Australasian Institute of Mining and Metallurgy and a Member of the Australian Institute of Geoscientists. He is a Registered Professional Geologist in Industrial Minerals. Dr Scogings has sufficient experience relevant to the style of mineralisation and type of deposit under consideration and to the activity which he is undertaking to qualify as Competent Person as defined in the 2012 Edition of the "Australasian Code for the Reporting of Exploration Results, Mineral Resources, and Ore Reserves". The information is extracted from the PFS announcement dated 25 September 2018 and is available to view on the Company's website at www.fyiresources.com.au . The Company confirms that it is not aware of any new information or data that materially affects the information included in the original announcement and that all

(MORE TO FOLLOW) Dow Jones Newswires