The Pilot is part of the
There has been considerable field activity since the last update. Each of the five new lease sites have been constructed along with road access and the installation of conductor pipe. The Silver City Rig 25 Schramm T200XD drill rig arrived on site last week and has commenced drilling operations, with the Glenaras 23 well spudding on Monday, 14th September. As at
As previously reported, the five Glenaras vertical wells will be drilled with the Silver City Rig 25 drill rig, with the full drilling program extending over 4-5 weeks (6-7 days/well). All five wells will be drilled vertically to just below the R7 coal resulting in a total depth of approximately 1050m. Further operational updates will be provided to the market throughout the drilling programme.