Genex Power Limited provided the following construction update in relation to the 250MW Kidston Pumped Storage Hydro Project (K2-Hydro or the Project) between the months of October and November 2021 (the Period). The construction schedule remains on track and on budget, and the Company continues to work closely with its principal construction contractors, McConnell Dowell and John Holland, to deliver the Project in Fourth Quarter CY2024. The Project construction continues progress to schedule with design progressing and key deliverables being met. Key activities on the Project and works undertaken at site during the Period include: Andritz Hydro successfully completed the model tests at their hydraulic laboratory in Graz, Austria for the 2 x 125MW turbines to be used for the Project; Completion of the airstrip upgrades to facilitate fly-in-fly-out operations for construction personnel, with 3 -4 flights arriving per week; Completion of the main Construction Site Office and workshops; Completion of onsite establishment of aggregate crushing plant and concrete batching plant, with aggregate crushing and concrete batching operations ongoing; Completion of main access road into the site; Completion of the refurbishment works for the Oaks Rush Accommodation Village, with main facility buildings and 450 bed camp expansion complete; Continuation of site infrastructure upgrades with mobile and Wi-Fi communications fully operational; Clearing and earthworks preparation for the two onsite switchyards, and Continuation of Main Access Tunnel (MAT) Portal face stabilisation works with the 12m high temporary access platform complete. Genex Power Limited (Genex or the Company) is pleased to provide the following construction update in relation to the 250MW Kidston Pumped Storage Hydro Project (K2-Hydro or the Project) between the months of October and November 2021 (the Period). The construction schedule remains on track and on budget, and the Company continues to work closely with its principal construction contractors, McConnell Dowell and John Holland, to deliver the Project in Fourth Quarter CY2024. The Project construction continues progress to schedule with design progressing and key deliverables being met. Key activities on the Project and works undertaken at site during the Period include: Andritz Hydro successfully completed the model tests at their hydraulic laboratory in Graz, Austria for the 2 x 125MW turbines to be used for the Project; Completion of the airstrip upgrades to facilitate fly-in-fly-out operations for construction personnel, with 3 -4 flights arriving per week; Completion of the main Construction Site Office and workshops; Completion of onsite establishment of aggregate crushing plant and concrete batching plant, with aggregate crushing and concrete batching operations ongoing; Completion of main access road into the site; Completion of the refurbishment works for the Oaks Rush Accommodation Village, with main facility buildings and 450 bed camp expansion complete; Continuation of site infrastructure upgrades with mobile and Wi-Fi communications fully operational; Clearing and earthworks preparation for the two onsite switchyards, and Continuation of Main Access Tunnel (MAT) Portal face stabilisation works with the 12m high temporary access platform complete.