Incitec Pivot Limited provided an update on operations at its Waggaman ammonia plant. On 15 February 2021, IPL advised that the Waggaman plant was expected to recommence operations by mid-March following the first planned turnaround since the plant was commissioned in 2016. Mechanical completion of the turnaround was completed on 6 March followed by startup activity through to 17 March, when the plant was brought down as a result of a dry gas seal failure and vibrations in the turbine on the induced draft fan. Additional investigations into the root causes of both issues have been completed and repairs are currently underway. IPL's current work plan is expected to result in production recommencing by mid-April.