28 November 2020

⁠Power engineers of the Tver branch of Rosseti Centre are completing the elimination of technological disruptions in power grids of the Tver region, caused by a powerful cyclone that night. Currently, there are no disconnected consumers in the 35-110 kV main grid.

The remaining consumers in the Zapadnodvinsky, Toropetsky, Ostashkovsky, Vyshnevolotsky and Bezhetsky districts of the Tver region will be supplied in the near future.

The power engineers were transferred to a special operating mode in advance and were provided with all the necessary forces and means to eliminate technological violations.

To eliminate technological violations, 75 crews of the branch were involved, consisting of 315 people and 92 specialized vehicles, as well as sources of backup power supply. Also, by decision of the company's management, the redeployment of the forces and means was made to strengthen problem areas and speed up the course of emergency recovery measures. In addition, 56 crews, 321 people and 63 vehicles were mobilized from other regions.

Immediate interaction with forces of the Ministry of Emergency Situations in the Tver region, the administration of the Tver region, the leadership of municipalities was organized. The power engineers of Rosseti Centre will continue to work until the full restoration of power supply to consumers.

You can report power outages and noticed damage to power facilities by calling Rosseti's contact centre's single free telephone number at 8-800-220-0-220 or through the svetlayastrana.rf portal. Calls from residents of the Tver region are accepted without delay.