Log in
E-mail
Password
Show password
Remember
Forgot password ?
Become a member for free
Sign up
Sign up
New member
Sign up for FREE
New customer
Discover our services
Settings
Settings
Dynamic quotes 
OFFON
  1. Homepage
  2. Equities
  3. Canada
  4. Toronto Stock Exchange
  5. Ivanhoe Mines Ltd.
  6. News
  7. Summary
    IVN   CA46579R1047

IVANHOE MINES LTD.

(IVN)
  Report
Delayed Quote. Delayed Toronto Stock Exchange - 12/03 05:00:00 pm
9.48 CAD   -1.35%
12/02Ivanhoe Mines Reports No Impact from the Omicron Variant on Any of Its Operations
NE
11/23London copper subdued on dollar strength
RE
11/23Zijin Approves $769 Million Congo Copper Smelter Investment
MT
SummaryQuotesChartsNewsRatingsCalendarCompanyFinancialsConsensusRevisions 
SummaryMost relevantAll NewsAnalyst Reco.Other languagesPress ReleasesOfficial PublicationsSector newsMarketScreener Strategies

Ivanhoe Mines : Kamoa-Kakula's Phase 2 expansion, doubling production to over 400,000 tonnes of copper per year, ahead of schedule and now on track to begin full operations in Q2 2022

10/13/2021 | 08:32am EST

October 12, 2021

Kamoa-Kakula's Phase 2 expansion, doubling production to over 400,000 tonnes of copper per year, ahead of schedule and now on track to begin full operations in Q2 2022

New Phase 1 daily production record of 721 tonnes of copper

achieved

Kamoa-Kakula's second filter press begins operations, allowing

for increased copper concentrate production

Phase 1 concentrator ore throughput exceeding the 3.8 Mtpa

design by more than 10%

KOLWEZI, DEMOCRATIC REPUBLIC OF CONGO - Ivanhoe Mines (TSX: IVN; OTCQX: IVPAF) Co-Chairs Robert Friedland and Yufeng "Miles" Sun announced that construction of Kamoa-Kakula's Phase 2 concentrator plant, which is designed to double copper production to approximately 400,000 tonnes a year, is proceeding ahead of schedule. The project team now anticipates beginning operations of the Phase 2 concentrator plant in Q2 2022, as compared to current guidance of Q3 2022.

Mark Farren, Kamoa Copper's CEO, stated: "Construction of the Phase 2 concentrator plant is progressing very well and the project team is working hard to complete the project ahead of schedule, similar to what we did with the Phase 1 plant. Based on the pace of the work completed to date, we now expect to deliver first ore to the Phase 2 ball mills before the end of Q2 2022."

The Phase 2, 3.8 million-tonne-per-annum (Mtpa) concentrator plant is a carbon copy of the Phase 1 concentrator plant, and is being constructed alongside the Phase 1 plant. All long-lead items of equipment, structural steel, platework and mechanical equipment for the Phase 2 plant already are delivered to site or are en-route. As of the end of September 2021, the Phase 2 plant was more than 50% complete.

"The ahead-of-schedule and on-budget achievements at Kamoa-Kakula stand tall and shine brightly in a COVID-19 world … where mining, infrastructure, and other industrial projects are routinely massively delayed, hindered by supply bottlenecks and predictably subject to significant cost over-runs. This outstanding construction progress at our Phase 1 and Phase 2 mines in this challenging environment is a testament to the extraordinary skill and dedication of our 'United Nations' of managers,

2

staff and contractors," said Ivanhoe Founder & Executive Co-Chair Robert Friedland. "Their careful and diligent planning, and their utilization of all of our inherent advantages, delivered this historic achievement, which the industry and the world can now plainly see has risen to new heights in what a recent industry publication called the 'Democratic Republic of Copper'.

"The Congolese mining industry has a very bright future indeed, and the legacy mining companies had better 'pull up their socks' … We are just starting … Having raised the bar for construction delivery, Ivanhoe Mines is setting its sights on raising the environmental, social and governance bar for the ultra-low-carbon copper production our world desperately needs for the energy transformation. We have all the pieces to do just that … We have the right team … We have the right partners and the right stakeholders. And we have the best copper projects in the world right now."

Also at the end of September, Kamoa-Kakula had surface ore stockpiles totalling approximately 3.66 million tonnes grading 4.73% copper, containing more than 173,000 tonnes of copper (or 381.4 million pounds of copper). These stockpiles are in place to help ensure a smooth and efficient ramp up of the Phase 2 concentrator to steady-state production during 2022.

As forecast in Ivanhoe's Kamoa-Kakula's progress update issued on September 30, the second concentrate filter press began operations on October 3, enabling the Phase 1 plant to produce copper concentrate above design parameters. The second filter allows Kamoa-Kakula's Phase 1 concentrator to take advantage of the exceptionally high- grade copper ore being processed directly from Kakula's underground mining operations and surface stockpiles.

"Kamoa-Kakula's Phase 1 milling and flotation capacity has been demonstrated to be in excess of design parameters," commented Steve Amos, Kamoa Copper's Head of Projects. "As such, the additional filter press enables Kamoa-Kakula to take advantage of the extra mill throughput to produce more copper than the estimated design output of approximately 200,000 tonnes per year. We have a third filter press on order that will be installed as part of the Phase 2 concentrator expansion.

"The additional filtration capacity also will allow Kamoa-Kakula's operations team to find the 'sweet spot' between copper recoveries and concentrate copper grades."

3

Aerial shot of the side-by-side Phase 1 (left) and Phase 2 (right) concentrator plants.

All eight rougher flotation cells and three of six cleaner flotation cells now installed in the Phase 2 concentrator plant.

4

Installing the inlet trunnion on the Phase 2 secondary ball mill.

Lifting the reducer gear box assembly for the Phase 2 secondary ball mill.

5

Preparing to lift shell sections of the second of two Phase 2 ball mills.

Since the previous reporting month, the Phase 1 concentrator has consistently achieved a run-rate throughput of 12,600 tonnes of ore per day (a rate of approximately

4.2 Mtpa), which is 10.5% higher than the design throughput of approximately 11,400 tonnes per day, or 3.8 Mtpa.

During initial commissioning of the second filter press, a new daily production record of 721 tonnes of copper in filtered concentrate was achieved on October 4, 2021. The current copper price is approximately US$9,500 a tonne.

Watch a short video showcasing the commissioning of the second concentrate filter press at Kamoa-Kakula:https://vimeo.com/629021616/deccdb4768

The Kamoa-Kakula Copper Project is a joint venture between Ivanhoe Mines (39.6%), Zijin Mining Group (39.6%), Crystal River Global Limited (0.8%) and the Government of the Democratic Republic of Congo (20%).

This is an excerpt of the original content. To continue reading it, access the original document here.

Disclaimer

Ivanhoe Mines Ltd. published this content on 12 October 2021 and is solely responsible for the information contained therein. Distributed by Public, unedited and unaltered, on 13 October 2021 12:31:08 UTC.


ę Publicnow 2021
All news about IVANHOE MINES LTD.
12/02Ivanhoe Mines Reports No Impact from the Omicron Variant on Any of Its Operations
NE
11/23London copper subdued on dollar strength
RE
11/23Zijin Approves $769 Million Congo Copper Smelter Investment
MT
11/23China's Zijin approves investment in $769 million Congo copper smelter
RE
11/18Kamoa Copper Awards China Nerin Engineering Contract for Direct-to-Blister Copper Smelt..
NE
11/17IVANHOE MINES : issues Q3 2021 financial results and review of operations, mine constructi..
PU
11/15Ivanhoe Mines Names New CFO
MT
11/15Ivanhoe Mines Swings to Q3 Profit, Lifts Production Guidance
MT
11/15IVANHOE MINES : Condensed consolidated interim financial statements for the period ended S..
PU
11/15IVANHOE MINES : Management's Discussion and Analysis for the period ended September 30, 20..
PU
More news
Analyst Recommendations on IVANHOE MINES LTD.
More recommendations
Financials (USD)
Sales 2021 264 M - -
Net income 2021 107 M - -
Net Debt 2021 - - -
P/E ratio 2021 78,5x
Yield 2021 -
Capitalization 8 921 M 8 956 M -
Capi. / Sales 2021 33,7x
EV / Sales 2022 11,1x
Nbr of Employees 710
Free-Float 46,5%
Chart IVANHOE MINES LTD.
Duration : Period :
Ivanhoe Mines Ltd. Technical Analysis Chart | MarketScreener
Full-screen chart
Technical analysis trends IVANHOE MINES LTD.
Short TermMid-TermLong Term
TrendsBearishBullishBullish
Income Statement Evolution
Consensus
Sell
Buy
Mean consensus OUTPERFORM
Number of Analysts 10
Last Close Price 7,38 $
Average target price 9,79 $
Spread / Average Target 32,7%
EPS Revisions
Managers and Directors
Martie Cloete President
David van Heerden Chief Financial Officer
Robert Martin Friedland Executive Co-Chairman
Yu Feng Sun Non-Executive Co-Chairman
Pierre Joubert Executive Vice President-Technical Services
Sector and Competitors
1st jan.Capi. (M$)
IVANHOE MINES LTD.38.19%8 956
BHP GROUP-5.19%140 349
RIO TINTO PLC-16.30%100 384
GLENCORE PLC51.03%61 034
ANGLO AMERICAN PLC15.49%44 004
GRUPO MÉXICO, S.A.B. DE C.V.8.48%33 156