September Quarter 2024 Presentation

Tony Ottaviano: Managing Director and CEO

Jon Latto: Chief Financial Officer

Adam Smits: Chief Operating Officer

30 October 2024

ASX: LTR

ltresources.com.au

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

ESG Performance - September Quarter 2024

Safety

TRIFR 5.68 LTIFR 0.32 (-)

Social

Female Workforce

21%

In line with industry benchmark

Environment

Renewable Penetration

86%

Governance

Material Reportable

incidents

Zero (-)

Notes:

  1. (-)designates metric unchanged
  2. LTIFR: Lost Time Injury Frequency Rate; TRIFR: Total Reportable Injury Frequency Rate representative of rolling annual averages

3

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

Production Highlights - September Quarter 2024

Mining

Processing

4.14Mt

282kt

total material mined for

processed in the quarter

the quarter

(Open pit: 3,957kt;

Underground: 187kt)

Production

Sales

28,171 dmt

10,831 dmt

spodumene concentrate

concentrate shipped

produced

(inaugural shipment, 5.33% grade)

Notes:

1.Production and plant metrics represent the period from first production; 31 July 2024 to 30 September 2024

Plant availability

87%

September month average

Lithia recovery

51%

September month average

4

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

Performance: Mining advancing at a steady drumbeat

Mining production

  • Continues to deliver across both open pit and underground with 4.14Mt total material mined for the quarter
  • Total stockpiles of 674kt at quarter end (including 309kt clean ore, 261kt ore sorted product (OSP), and 104kt of post-crushed ore)

Underground

  • Approaching 12 months of underground development (in November 2024)
  • Strong jumbo development rates of 311 metres per jumbo per month achieving 1,869 development metres for the quarter
  • First development ore successfully extracted from Mt Mann in August 2024, contributing 19kt of ore to the clean ore stockpile

Open Pit

  • Well advanced with production of 3.95Mt moved in the quarter and the mining from the main ore zone contributing in-line with schedule

5

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

Performance: Improving key process plant metrics

Upward trend and improving variability across all key metrics - mill availability, throughput and recovery

Plant availability

  • Consistently exceeding greater than 80% from week 3
  • Average mill availability of 87% in September, with ~99% availability achieved in the last week of September
  • 82% availability recorded in week 7 due to mill offline for planned plant adjustments

Lithia recovery:

  • Progressing in line with expectations, averaging 51% in September
  • Ongoing optimisation work to continue improvement in lithia recovery and throughput rates

Subsequent to quarter end:

  • Tantalum circuit commissioning commenced post-quarter end, yielding ~70t of concentrate grading over 4.5% Ta to 28 October 2024

Notes:

  1. Charts show actual performance from first ore feed to mill i.e. includes all ore commissioning activities and ramp up
  2. Orange line denotes trend line

6

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

Performance: delivering production to plan

Strong throughput, concentrate output and first shipment achieved within the first quarter of production ramp-up

Spodumene concentrate production:

~28kt spodumene concentrate produced at an average concentrate grade of 5.2% Li2O

Mill throughput:

Achieved ~282kt, exceeding ramp-up targets for August and September

Crushing circuit achieved 3Mtpa annualised nameplate (on an instantaneous basis) as required over the course of the quarter

Wet circuit stability improved over the quarter, enhancing recovery and throughput

Plant design:

Whole of Ore flowsheet providing stable platform for progressive improvement, as expected

Significant optimisation levers available to drive further step change in efficiencies

Notes:

1.

Charts show actual performance from first ore feed to mill i.e. includes all ore commissioning activities and ramp up

2.

Week 9 performance reflects a partial week (5 days)

7

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

Performance: Strong start to shipments and offtakes

Initiated spot sales strategy to improve overall realised pricing and ensure market transparency

Sales:

  • Inaugural shipment of 10,831dmt of spodumene concentrate, grading 5.33% Li20, departed Port of Geraldton on 27 September 2024
  • Executed spot sale of 10,000 tonnes to a Singapore-based trader at reference price of US$802 per dmt SC6, above the market spot price at the time of execution. Cargo sailed on 26 October 2024
  • Sales proceeds from this quarter's shipment will be recognised in the December 2024 quarter

Offtake agreements:

  • Strategic Offtake Agreements planned to progressively be delivered as production ramps-up
  • Offtake review with Ford was completed during the quarter resulting in a pricing reference amendment to lithium carbonate rather than hydroxide, and agreement to commence supply on or after 1 July 2025

8

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

Cashflows reflect transition into production

Cash increased by $140M to $263M as at 30 September 2024

Notes:

  1. US$250M Convertible Notes at 0.6715 exchange rate
  2. All $M in chart above are in AUD unless otherwise stated
  • Convertible notes: A$372M1 received as part of expanded strategic partnership with LG Energy Solution, aimed at funding ramp-up and working capital
  • Operating costs: $52M of operating costs, including open pit mining, processing, maintenance, site administration, and corporate costs
  • Capital expenditure: $29M invested in underground mine development and deferred waste at Kathleen's Corner Open Pit
  • Kathleen Valley (KV) project expenditure: $81M spent on construction during the quarter completing the works
  • Capital - Other: $69M which includes commissioning costs and capital projects not required for first production (e.g. paste fill plant)

Once in steady-state (end Q1CY2025) and project

expenditure finalises, the Company anticipates

operating and capital cashflows to normalise

9

NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES

Business optimisation - strong through the cycle

Company-wide focus to increase productivity and sustainably reduce costs to further strengthen our position as a Tier-1 producer

Relentless focus

on productivity

  • Transition from developer to operator while maintaining operating discipline and continuous improvement
  • Investment in systems and processes through our business readiness phase has enabled strong start to ramp-up
  • Every area of corporate and operations is under continuous review to improve outcomes and reduce costs
  • Review well advanced to optimise ore feed throughputs and reduce costs in response to market conditions,

Mine planwhile retaining flexibility to expand when lithium prices improve

optimisation

Anticipate providing an update to the market on outcomes by the end of CY2024

Reducing all

Review of all input costs is ongoing for both required quantities and current 'best' prices

input costs

Re-negotiations with suppliers in progress to reflect current market conditions and our requirements

Optimising

All capital spend is being reviewed and either optimised, deferred or removed

Implementing capital allocation process to drive internal competition and drive highest-value outcomes

capital

allocation

Continuing to efficiently use sustaining capital for mine development

10

Attention: This is an excerpt of the original content. To continue reading it, access the original document here.

Attachments

  • Original document
  • Permalink

Disclaimer

Liontown Resources Limited published this content on October 30, 2024, and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on October 30, 2024 at 00:12:09.238.