September Quarter 2024 Presentation
Tony Ottaviano: Managing Director and CEO
Jon Latto: Chief Financial Officer
Adam Smits: Chief Operating Officer
30 October 2024
ASX: LTR | ltresources.com.au |
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
ESG Performance - September Quarter 2024
Safety
TRIFR 5.68 ↓ LTIFR 0.32 (-)
Social
Female Workforce
21% −
In line with industry benchmark
Environment
Renewable Penetration
86% −
Governance
Material Reportable
incidents
Zero (-)
Notes:
- (-)designates metric unchanged
- LTIFR: Lost Time Injury Frequency Rate; TRIFR: Total Reportable Injury Frequency Rate representative of rolling annual averages
3
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
Production Highlights - September Quarter 2024
Mining | Processing |
4.14Mt | 282kt |
total material mined for | processed in the quarter |
the quarter |
(Open pit: 3,957kt;
Underground: 187kt)
Production | Sales |
28,171 dmt | 10,831 dmt |
spodumene concentrate | concentrate shipped |
produced | (inaugural shipment, 5.33% grade) |
Notes:
1.Production and plant metrics represent the period from first production; 31 July 2024 to 30 September 2024
Plant availability
87%
September month average
Lithia recovery
51%
September month average
4
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
Performance: Mining advancing at a steady drumbeat
Mining production
- Continues to deliver across both open pit and underground with 4.14Mt total material mined for the quarter
- Total stockpiles of 674kt at quarter end (including 309kt clean ore, 261kt ore sorted product (OSP), and 104kt of post-crushed ore)
Underground
- Approaching 12 months of underground development (in November 2024)
- Strong jumbo development rates of 311 metres per jumbo per month achieving 1,869 development metres for the quarter
- First development ore successfully extracted from Mt Mann in August 2024, contributing 19kt of ore to the clean ore stockpile
Open Pit
- Well advanced with production of 3.95Mt moved in the quarter and the mining from the main ore zone contributing in-line with schedule
5
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
Performance: Improving key process plant metrics
Upward trend and improving variability across all key metrics - mill availability, throughput and recovery
Plant availability
- Consistently exceeding greater than 80% from week 3
- Average mill availability of 87% in September, with ~99% availability achieved in the last week of September
- 82% availability recorded in week 7 due to mill offline for planned plant adjustments
Lithia recovery:
- Progressing in line with expectations, averaging 51% in September
- Ongoing optimisation work to continue improvement in lithia recovery and throughput rates
Subsequent to quarter end:
- Tantalum circuit commissioning commenced post-quarter end, yielding ~70t of concentrate grading over 4.5% Ta to 28 October 2024
Notes:
- Charts show actual performance from first ore feed to mill i.e. includes all ore commissioning activities and ramp up
- Orange line denotes trend line
6
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
Performance: delivering production to plan
Strong throughput, concentrate output and first shipment achieved within the first quarter of production ramp-up
Spodumene concentrate production:
• ~28kt spodumene concentrate produced at an average concentrate grade of 5.2% Li2O
Mill throughput:
• Achieved ~282kt, exceeding ramp-up targets for August and September
• Crushing circuit achieved 3Mtpa annualised nameplate (on an instantaneous basis) as required over the course of the quarter
• Wet circuit stability improved over the quarter, enhancing recovery and throughput
Plant design:
• Whole of Ore flowsheet providing stable platform for progressive improvement, as expected
• Significant optimisation levers available to drive further step change in efficiencies
Notes: | ||
1. | Charts show actual performance from first ore feed to mill i.e. includes all ore commissioning activities and ramp up | |
2. | Week 9 performance reflects a partial week (5 days) | 7 |
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
Performance: Strong start to shipments and offtakes
Initiated spot sales strategy to improve overall realised pricing and ensure market transparency
Sales:
- Inaugural shipment of 10,831dmt of spodumene concentrate, grading 5.33% Li20, departed Port of Geraldton on 27 September 2024
- Executed spot sale of 10,000 tonnes to a Singapore-based trader at reference price of US$802 per dmt SC6, above the market spot price at the time of execution. Cargo sailed on 26 October 2024
- Sales proceeds from this quarter's shipment will be recognised in the December 2024 quarter
Offtake agreements:
- Strategic Offtake Agreements planned to progressively be delivered as production ramps-up
- Offtake review with Ford was completed during the quarter resulting in a pricing reference amendment to lithium carbonate rather than hydroxide, and agreement to commence supply on or after 1 July 2025
8
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
Cashflows reflect transition into production
Cash increased by $140M to $263M as at 30 September 2024
Notes:
- US$250M Convertible Notes at 0.6715 exchange rate
- All $M in chart above are in AUD unless otherwise stated
- Convertible notes: A$372M1 received as part of expanded strategic partnership with LG Energy Solution, aimed at funding ramp-up and working capital
- Operating costs: $52M of operating costs, including open pit mining, processing, maintenance, site administration, and corporate costs
- Capital expenditure: $29M invested in underground mine development and deferred waste at Kathleen's Corner Open Pit
- Kathleen Valley (KV) project expenditure: $81M spent on construction during the quarter completing the works
- Capital - Other: $69M which includes commissioning costs and capital projects not required for first production (e.g. paste fill plant)
Once in steady-state (end Q1CY2025) and project | |
expenditure finalises, the Company anticipates | |
operating and capital cashflows to normalise | 9 |
NOT FOR RELEASE OR DISTRIBUTION IN THE UNITED STATES
Business optimisation - strong through the cycle
Company-wide focus to increase productivity and sustainably reduce costs to further strengthen our position as a Tier-1 producer
Relentless focus |
on productivity |
- Transition from developer to operator while maintaining operating discipline and continuous improvement
- Investment in systems and processes through our business readiness phase has enabled strong start to ramp-up
- Every area of corporate and operations is under continuous review to improve outcomes and reduce costs
- Review well advanced to optimise ore feed throughputs and reduce costs in response to market conditions,
Mine planwhile retaining flexibility to expand when lithium prices improve
optimisation | • Anticipate providing an update to the market on outcomes by the end of CY2024 |
Reducing all | • Review of all input costs is ongoing for both required quantities and current 'best' prices | |
input costs | • Re-negotiations with suppliers in progress to reflect current market conditions and our requirements | |
Optimising | • All capital spend is being reviewed and either optimised, deferred or removed | |
• Implementing capital allocation process to drive internal competition and drive highest-value outcomes | ||
capital | ||
allocation | • Continuing to efficiently use sustaining capital for mine development |
10
Attention: This is an excerpt of the original content. To continue reading it, access the original document here. |
Attachments
- Original document
- Permalink
Disclaimer
Liontown Resources Limited published this content on October 30, 2024, and is solely responsible for the information contained herein. Distributed by Public, unedited and unaltered, on October 30, 2024 at 00:12:09.238.