Lithium Plus Minerals Ltd. announced that diamond drilling at its Bynoe Lithium Project is set to commence this week. Darwin-based contractor, May Drilling, has been contracted to undertake an initial two-phase, 1,800m diamond drilling program at the Lei Prospect. Drill pad preparation works are complete and the locally based diamond drill rig has been mobilised to site. Phase 1 encompasses three holes for approximately 600m. It is designed to build on the historic Lei discovery hole of 12m at 1.43% Li2O. Results from Phase 1 are set to provide detailed characterisation and key structural information to support further drill planning. Phase 2 is targeted to include up to 6 holes over 1,200m. It is set to follow the previously announced
Reverse Circulation (RC) drilling program and target further definition of lithium bearing pegmatites at the Lei Prospect. The initial RC drilling program at Lei and Cai is on track to begin during July 2022. This program comprises approximately 10,000m and is expected to take approximately four months to complete.