Fresnillo plc (“Fresnillo”) and MAG Silver Corp. (“MAG Silver”) provided a commissioning update on the Juanicipio Project (56% /44% Fresnillo and MAG Silver, respectively). The Juanicipio Project team delivered the Project for plant commissioning on schedule despite the recent changes to labour contracting legislation and having successfully mitigated most COVID-19 related issues over the past two years, a testament to the dedication of the operational and development teams on the ground.

However, the ‘Comisión Federal de Electricidad' (“CFE”), the state-owned electrical company, has just notified Fresnillo, the Juanicipio Project operator, that approval to complete the tie-in to the national power grid cannot yet be granted and the mill commissioning timeline will therefore be extended by approximately six months. This is directly related to knock-on effects of the pandemic on the CFE's operations, predominantly related to a lack of CFE staff which limits its ability to oversee three key tasks to: review the existing installation; supervise physical connection to the active power grid; and approve required blackout prevention devices. As operator, Fresnillo will continue to engage closely with the CFE and ‘El Centro Nacional de Control de Energía' (“CENACE”) to do all that it can to expedite these necessary approvals.

Although there remains uncertainty regarding the timing for connecting the Juanicipio Project to the power grid, the current estimate, which continues to be subject to potential COVID-19 related realities, is that full load commissioning activities will be approved sometime after the first week of May 2022. Stoping and mineralized mine development at Juanicipio will continue. In order to minimize any potential adverse effect, Fresnillo will make available any unused plant capacity at its Minera Fresnillo and Minera Saucito operations to process mineralized material produced at Juanicipio during this period, and if possible matching commissioning and ramp up tonnages that were previously expected.

The effect on cashflow generation from Juanicipio therefore will also be mitigated while CFE approvals are pending.