All amounts herein are reported in $000s of
HIGHLIGHTS –
OPERATIONAL
- Positive progress was achieved during the quarter ended
June 30, 2021 on the construction of the 4,000 tpd Juanicipio processing plant and civil works:- Mechanical installation of the flotation cells and filters were completed during the Q2 2021;
- The SAG and ball mills were installed during Q2 2021; and,
- Underground development has reached approximately 40 km (25 miles), and the first cut and fill stope has been opened and a trial longhole stope is being tested.
- As reported by the operator Fresnillo, the Juanicipio plant is expected to come in on budget and as scheduled to commence commissioning in Q4 2021, reaching 40 to 50% of its 4,000 tonnes per day (“tpd”) nameplate capacity by the end of 2021 and reaching 90 to 95% of its nameplate capacity in 2022.
- A regularly updated photo gallery of construction progress at Juanicipio is available at https://magsilver.com/projects/photo-gallery/#photo-gallery.
- Batch processing of mineralized material from development headings continues through the nearby Fresnillo plant at a targeted two days per month of continuous processing for a nominal expected rate of 16,000 tonnes per month.
- For the three months ended
June 30, 2021 , on a 100% basis:- 44,435 tonnes of mineralized material were processed through the Fresnillo plant, with 404,518 payable silver ounces, 709 payable gold ounces, 133 tonnes of lead and 209 tonnes of zinc produced and sold; and,
- Pre-commercial production sales totaled
$11,256 for the quarter (net of treatment and processing costs), less$2,373 in mining and transportation costs, netting$8,883 recorded as gross profit by Minera Juanicipio in the quarter.
- For the six months ended
June 30, 2021 , on a 100% basis:- 80,830 tonnes of mineralized material were processed through the Fresnillo plant, with 835,706 payable silver ounces, 1,340 payable gold ounces, 270 tonnes of lead and 408 tonnes of zinc produced and sold;
- Average silver head grade of 405 grams per tonne (“g/t”) of the material processed; and
- Pre-commercial production sales of
$21,341 for the six month period (net of treatment and processing costs) less$4,259 in mining and transportation costs, netting$17,082 recorded as year to date gross profit by Minera Juanicipio.
- Since
August 2020 , 152,689 tonnes of mineralized development material have been processed through the Fresnillo plant, which is expected to:- contribute cash-flow to offset some of the initial project capital; and
- significantly speed up project ramp-up due to the de-risking of Juanicipio’s metallurgical performance.
- Juanicipio capex is estimated at
$440,000 (100% basis) as ofJanuary 1, 2018 , less approximately$313,400 in development expenditures incurred from then toJune 30, 2021 leaving approximately$126,600 of remaining initial capital on a 100% basis (MAG’s 44% estimated at$55,704 ) as atJune 30, 2021 . The cash required will be reduced by:- Existing cash held in Minera Juanicipio as at
June 30, 2021 ($15,107 on a 100% basis); and, - Expected cashflow generated from mineralized material being processed through the Fresnillo plant up until the Juanicipio plant commences commissioning in Q4 2021.
- Existing cash held in Minera Juanicipio as at
- A further 14,207 tonnes of development material were processed in
July 2021 .
EXPLORATION
- In spite of temporary COVID-19 restrictions established by the Mexican Government in 2020, the full Juanicipio 2020 exploration program was completed as planned with 33 surface holes (27,900 metres (“m”)) and 77 underground definition holes (11,800 m) completed. Assays were reported subsequent to the quarter end (see Press Release dated
August 5, 2021 ), and the program successfully:- Confirms, and allows modeling with greater detail and confidence of the high-grade silver resource within the upper parts of the Valdecañas
Bonanza Zone (as defined in the 2017 PEA) where the first several years of mining will occur; - Confirms, expands, and allows improved modeling of the continuous wide mineralization of the Valdecañas
Deep Zone (as defined in the 2017 PEA); and, - Confirms, expands, and allows improved modeling of the ever-growing Anticipada Vein.
- Confirms, and allows modeling with greater detail and confidence of the high-grade silver resource within the upper parts of the Valdecañas
- The 2021 Juanicipio Exploration program is budgeted at
$6 million on a 100% basis, and is to be evenly allocated between continued step-out and infill drilling of the Valdecañas Vein System (including independent targeting of the Venadas Vein family and the Anticipada Vein) and three principal target areas elsewhere in the Joint Venture ground.
- Five drill rigs are presently on surface running concurrently with continued underground definition drilling.
Deer Trail Project inUtah :- Phase I drilling was completed in Q2 2021 with assays pending and expected to be released during the third quarter of 2021.
- Subsequent to the quarter end, a 5 hole/5,000 metre Phase II drill program commenced and is in process.
LIQUIDITY AND CAPITAL RESOURCES
- As at
June 30, 2021 , MAG held cash of$66,342 while Minera Juanicipio had cash on hand on a 100% basis of$15,107 .
CORPORATE
- MAG continues to refresh its board, as Mr.
Derek White did not stand for re-election at the Company’s Annual General and Special Meeting onJune 21, 2021 , and subsequent to the quarter end onAugust 3, 2021 , Mr.Dale Peniuk was appointed to the board.Mr. Peniuk is a Chartered Professional Accountant (CPA, CA) and corporate director.Mr. Peniuk currently serves on the board and as audit committee chair of Lundin Mining Corporation, Capstone Mining Corp. and Argonaut Gold Inc., and has been on the board and chair of the audit committee of numerous other Canadian public mining companies since 2006.Mr. Peniuk obtained his Bachelor of Commerce degree from theUniversity of British Columbia in 1982 and his Chartered Accountant designation from theInstitute of Chartered Accountants of British Columbia (now the Chartered Professional Accountants ofBritish Columbia ) in 1986, and spent more than 20 years withKPMG LLP Chartered Accountants and predecessor firms, the last 10 of which as an assurance partner with a focus on mining companies, including leading KPMG’sVancouver office mining industry group.
JUANICIPIO PROJECT UPDATE
During Q2 2021, continued progress was achieved on the construction of the Juanicipio processing plant. The SAG and ball mills were installed during the quarter, and mechanical installation of the flotation cells and filters were completed during the Q2 2021. All major mechanical pieces have now been installed. The tailings and concentrate thickeners are nearing completion. Significant progress has occurred on the initial tailings storage facility, and on the fine ore bin and stockpile dust cover. The lead and zinc flotation cell lines have been installed and are now piped in for air, water and froth flow. Underground development to date at Juanicipio is now approximately 40 km (25 miles) with access to the upper portion of the resource now achieved. Underground development priorities include continuing advance of the three internal spiral footwall production ramps designed to access the full strike length of the Valdecañas Vein system. Initial development indicates that the grade and width of the vein are in line with previous drilling-derived estimates.
According to Fresnillo, the operator, the Juanicipio processing plant is expected to come in on budget and as scheduled to commence commissioning in fourth quarter 2021 reaching 40 to 50% of nameplate capacity by the end of 2021 and achieving 90 to 95% of nameplate capacity in 2022.
The estimated project capital cost on a 100% basis, as estimated from
A regularly updated photo gallery of construction progress at Juanicipio is available at https://magsilver.com/projects/photo-gallery/#photo-gallery.
Underground Mine Production
As of August of 2020, mineralized material from development is being batch processed, refined and sold on commercial terms at a targeted rate of 16,000 tonnes per month at the nearby Fresnillo plant. The actual amount of material processed on a monthly basis fluctuates due to the variability of mineralization encountered in the development headings from month to month. In the three and six months ended
Table 1: Development Material Processed at Fresnillo’s Processing Plant (100% basis)
Payable Metals | Quantity 3 months, | Average Per Unit (1) 3 months | $ Amount 3 months | $ Amount 6 months | $ Amount 3 months & 6 months | |
Silver | 404,518 ounces | - | ||||
Gold | 709 ounces | - | ||||
Lead | 133 tonnes | - | ||||
Zinc | 209 tonnes | - | ||||
Treatment and refining and other processing charges | - | |||||
Provisional sales adjustment related to prior periods (3) | - | |||||
$11,256 | $21,341 | - | ||||
Mining and transportation costs | - | |||||
Gross Profit | $8,883 | $17,082 | - |
(1) | Ounces (“oz”) for silver and gold; and, pounds (“lb”) for lead and zinc. |
(2) | Underground mine production of development material commenced in August of 2020, so there are no comparable 2020. |
(3) | Provisional sales for 2020 were finalized in Q1 2021 resulting in negative adjustment to net sales revenue of |
By bringing forward the start-up of the underground mine and processing mineralized development material at the Fresnillo plant in advance of commissioning the Juanicipio plant, MAG and Fresnillo expect to secure several positive outcomes for the
- generating cash-flow from production to offset some of the cash requirements of the initial project capital;
- de-risking the flotation process through a better understanding of the metallurgical characteristics and response of the Juanicipio mineralization;
- increased certainty around the geological block model prior to start-up of the processing plant; and
- allowing for a faster and more certain ramp-up to the nameplate 4,000 tpd plant design.
Juanicipio Exploration Update
Despite a temporary COVID-19 exploration halt imposed by the Mexican Government in 2020, the full Juanicipio 2020 drilling program was completed as planned in 2020, although processing of assays was delayed and only released subsequent to the quarter ended
A complete set of tables by vein of the 2020 drilling results is available at: https://magsilver.com/site/assets/files/5810/nr-mar3-2020-table1-sdadds.pdf along with a new 3D video displaying the entire Valdecañas Vein System, available at:
https://magsilver.com/site/assets/files/5810/SSMovieHQ2_3-Mar3-2019-sdsawe.mp4 .
The 2020 drilling program successfully:
- Confirms, and allows modeling with greater detail and confidence of the high-grade silver resource within the upper parts of the Valdecañas
Bonanza Zone where the first several years of mining will occur; - Confirms, expands, and allows improved modeling of the continuous wide mineralization of the Valdecañas
Deep Zone ; and, - Confirms, expands, and allows improved modeling of the ever-growing Anticipada Vein.
DEER TRAIL PROJECT UPDATE
A Phase I surface-based core drilling program was completed during Q2 2021. Assays and interpretations are expected to be released during Q3 2021. A follow-up Phase II drill program was planned as interpretation of the incoming core and draft lab results were incorporated into the district geological model. Phase II drilling commenced subsequent to the quarter end in
Qualified Person: Dr.
FINANCIAL RESULTS – THREE AND SIX MONTHS ENDED
As at
The Company’s net income for three months ended
Table 2: MAG’s 44% share of income from its equity investment in Juanicipio
Three Months | Three Months | Six Months | Six Months | |||||||||
Gross Profit from processing development material (see Underground Mine Production – | $8,883 | Nil (1) | $17,082 | Nil (1) | ||||||||
Administrative expenses | $(287 | ) | Nil | $(655 | ) | Nil | ||||||
Foreign exchange and other | $(3,558 | ) | ||||||||||
Net income (loss) before tax | $9,795 | $317 | $16,551 | $(3,558 | ) | |||||||
Income tax benefit (expense) (including deferred income tax) | $(4,160 | ) | $(4,392 | ) | ||||||||
Net income (loss) for the period (100% basis) | $10,955 | $2,701 | $ 12,391 | $(7,950 | ) | |||||||
MAG’s 44% income (loss) - equity investment in Juanicipio | $4,820 | $1,189 | $5,452 | $(3,498 | ) |
About
Neither the
This release includes certain statements that may be deemed to be “forward-looking statements” within the meaning of the US Private Securities Litigation Reform Act of 1995. All statements in this release, other than statements of historical facts are forward looking statements, including statements that address future mineral production, reserve potential, exploration drilling, exploitation activities and events or developments. Forward-looking statements are often, but not always, identified by the use of words such as "seek", "anticipate", "plan", "continue", "estimate", "expect", "may", "will", "project", "predict", "potential", "targeting", "intend", "could", "might", "should", "believe" and similar expressions. These statements involve known and unknown risks, uncertainties and other factors that may cause actual results or events to differ materially from those anticipated in such forward-looking statements. Although MAG believes the expectations expressed in such forward-looking statements are based on reasonable assumptions, such statements are not guarantees of future performance and actual results or developments may differ materially from those in the forward-looking statements. Factors that could cause actual results to differ materially from those in forward-looking statements include, but are not limited to, changes in commodities prices, changes in mineral production performance, exploitation and exploration successes, continued availability of capital and financing, and general economic, market or business conditions, political risk, currency risk and capital cost inflation. In addition, forward-looking statements are subject to various risks, including that data is incomplete and considerable additional work will be required to complete further evaluation, including but not limited to drilling, engineering and socio-economic studies and investment. The reader is referred to the MAG’s filings with the
Please Note: Investors are urged to consider closely the disclosures in MAG's annual and quarterly reports and other public filings, accessible through the Internet at www.sedar.com and www.sec.gov LEI: 254900LGL904N7F3EL14
For further information on behalf ofMAG Silver Corp. ContactMichael J. Curlook , VP Investor Relations and Communications Phone: (604) 630-1399 Toll Free: (866) 630-1399 Website: www.magsilver.com Email: info@magsilver.com
Source:
2021 GlobeNewswire, Inc., source