9 August 2022: Magnora, a Norwegian renewable energy development company,
releases its financial report for the second quarter 2022.

Highlights:

 * Soaring electricity prices, both spot and longer term, energy security as
   well as reduction of CO2 footprint are all factors driving interest for our
   portfolio companies and their projects. We see stronger interest of doing
   business with our portfolio companies compared with previous quarters.
 * Magnora is pleased to announce its first guidance for its renewable
   portfolio. Magnora expects its net share of asset sales in the portfolio
   companies to be 150-250 MW for the full year 2022 at very attractive prices.
 * Magnora increased its ownership in Evolar AB to 63.5 percent according to
   business plan milestones.
 * Evolar has reached several key technical milestones and established supply
   chain for its sub-contractors. Additional discussions have been initiated
   during the quarter with very interesting customers and potential partners.
   Evolar will soon disclose its technical progress in several areas.
 * Helios closed additional sales of projects during the second quarter and has
   closed sales of 370 MW. The company also signed landowner agreements in
   Lithuania and Latvia, expanding its operations beyond Sweden. Helios
   management continues to deliver ahead of its business plan. Helios decided to
   distribute SEK 16 million to its owners in August 2022 in an extraordinary
   general meeting based on multiple sales and pre-payments. This is the first
   dividend from Helios. The dividend was limited to free equity in the company
   at 31.12.2021. Helios will pay out all excess cash to its shareholders going
   forward. Based on existing contracts over the last months and customer
   acceptance, Helios should be in a position to return hundreds of million SEK
   over the next few years to its owners
 * Magnora South Africa reached key milestones for several projects and are in
   close discussion with the National grid company about grid connection offers
   for 650 MW in several projects.
 * Magnora Offshore Wind AS (Magnora ASA owns 80 percent) signed Option to Lease
   Agreement with the Crown Estate Scotland for the N3 site, securing
   exclusivity for project development on the site. The payment is secured by
   long-term financing from a leading Norwegian bank. Magnora Offshore Wind
   entered into a cooperation agreement with Hiraeth Energy in Wales.
 * Kustvind has completed most of the wildlife and marine environmental studies
   without red flags.
 * Magnora entered the fast-growing UK Solar PV and battery storage market
   during the quarter through partnering with an experienced local developer.
   The Group now has 60 MW solar PV and 70 MW of battery storage under
   development in the UK in three different projects.
 * Adjusted EBITDA for second quarter 2022 was negative NOK 1.1 million. EBITDA
   was impacted by consolidating Evolar and higher development cost in Magnora
   Offshore Wind from the ScotWind project.
 * The Group secured NOK 100 million in longer term financing through a top tier
   bank. This replaces a facility of NOK 50 million, while the other loan
   facility of NOK 50 million is maintained. Total loan facility is now NOK 150
   million. As of 30 June 2022, NOK 62.5 million was drawn from the loan
   facility, leaving NOK 87.5 million of the total NOK 150 million loan
   facility. The Group has NOK 85.4 million in cash and loan facility available
   as of 4 August 2022.
 * Magnora Offshore Wind signed after the close of the quarter an Investment
   Shareholder Agreement (ISA) for the development of floating offshore wind
   projects in the Celtic Sea (Wales).
 * The Penguins FPSO is, according to Shell's Q2 2022 report expected to leave
   the yard and start production in 2022/23. According to media articles,
   sail-away is scheduled in the second half of this year which will release the
   first of three remaining license payments from Shell. First payment is USD
   7.5 million, and subsequent payments are USD 4.3 million at first oil and USD
   4.3 million at 4 million barrels of oil offloaded.
 * Interest for renewable projects have increased significantly over the last
   year and we see that many buyers want to close acquisition processes prior to
   the Ready-to-Build phase with substantial pre-payment instalments. In
   addition, we notice significant interest for private portfolios at prices
   above what we have guided for in the quarter for projects that have not
   entered the Ready-To-Build phase yet. 

 The second quarter report and presentation are attached to this announcement.

 The report can also be found on: https://magnoraasa.com/investors

 The company will host a webcast presentation at 10:00 CET this morning, which
can be accessed with the following link: 
https://streams.eventcdn.net/magnoraasa/2022-q2/

 The presentation will be followed by a Q&A session with the management.
Questions may be asked in writing during and after the presentation.

DISCLOSURE REGULATION

This information is subject to the disclosure requirements pursuant to section
5-12 of the Norwegian Securities Trading Act.

CONTACTS

 * Erik Sneve, CEO, email: es at magnoraasa.com 
 * Torstein Sanness, Executive chairman, email: sanness at sf-nett.no 

ABOUT MAGNORA ASA

Magnora ASA (OSE: MGN) has a legacy royalty business that is re-invested in
renewable energy development projects and companies. Magnora's portfolio of
renewable companies consists of Evolar AB, Helios Nordic Energy AB, Kustvind AB,
Magnora Offshore Wind AS, Magnora South Africa, and AGV. The company is listed
on the main list on Oslo Stock Exchange under the ticker MGN. 

ATTACHMENTS

Download announcement as PDF.pdf -
https://kommunikasjon.ntb.no/ir-files/17847805/1644/2216/Download%20announcement
%20as%20PDF.pdf

Magnora ASA Q2 2022 Report.pdf -
https://kommunikasjon.ntb.no/ir-files/17847805/1644/2214/Magnora%20ASA%20Q2%2020
22%20Report.pdf

Magnora ASA Q2 2022 Presentation.pdf -
https://kommunikasjon.ntb.no/ir-files/17847805/1644/2215/Magnora%20ASA%20Q2%2020
22%20Presentation.pdf

Click here for more information

© Oslo Bors ASA, source Oslo Stock Exchange