Metro Mining Limited reported production results for the month, quarter and year to date ended October 2019. For the month, the company reported bauxite mined of 479,000 WMT and bauxite shipped of 504,000 WMT. Bauxite mined per day of 15,452 WMT and bauxite shipped per day of 16,260 WMT.

For the quarter, the company reported bauxite mined of 479,000 WMT and bauxite shipped of 504,000 WMT. Bauxite mined per day of 15,452 WMT and bauxite shipped per day of 16,230 WMT.

For the year to date, the company reported bauxite mined of 2,779,000 WMT and bauxite shipped of 2,756,000 WMT.

The company anticipate a strong finish to the 2019 operating season and Bauxite Hills remains on track to meet the production and shipping guidance of 3.3-3.5 million WMT for 2019.